Heavy Construction — Otsego, New York

WD NY20260037-16125-hvy · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS/INSULATOR WORKER in Otsego, New York (construction type: heavy) is $43.25/hr base + $27.29/hr fringe = $70.54/hr total package (WD NY20260037-16125-hvy, Rev. 2).

Scroll down for all 57 trade classifications covered by this determination.

WD Number: NY20260037-16125-hvy
Revision: 2
Construction Type: heavy
State: New York (NY)
County: Otsego
Effective: May 17, 2026
Trades covered: 57
Official source: SAM.gov reference NY20260037View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS/INSULATOR WORKER $43.25 $27.29 $70.54 Top 10% $0.00 $0.00 $0.00 $0.00
BOILERMAKER $43.34 $27.66 $71.00 +97% vs market $0.00 $0.00 $0.00 $0.00
CABLE SPLICER $55.55 $35.03 $90.58 Above median $0.00 $0.00 $0.00 $0.00
CABLE SPLICER $50.43 $33.29 $83.72 Above median $0.00 $0.00 $0.00 $0.00
CARPENTER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING AND CHRISTMAS $44.52 $27.16 $71.68 +134% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON $38.63 $25.05 $63.68 Above median +110% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $50.50 $35.03 $85.53 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $48.00 $32.09 $80.09 Top 10% +115% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $42.68 $33.06 $75.74 Above median +103% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLU $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRID $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TR $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATIO $40.81 $6.99 $47.80 Top 10% +28% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DA $20.53 $6.39 $26.92 Top 10% -28% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NE $38.73 $6.93 $45.66 Top 10% +23% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $42.29 $30.66 $72.95 +96% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $52.86 $35.60 $88.46 Top 10% +138% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $47.57 $31.03 $78.60 Above median +111% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $31.72 $29.87 $61.59 Bottom 10% +65% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER $63.14 $33.82 $96.96 Top 10% +160% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid $64.59 $42.92 $107.51 Top 10% +189% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN $35.34 $30.12 $65.46 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or ga $35.34 $30.12 $65.46 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR $55.40 $31.78 $87.18 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail t $55.40 $31.78 $87.18 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type undergro $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type un $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or g $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR CONSTRUCTOR FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY $57.73 $38.44 $96.17 +61% vs market $0.00 $0.00 $0.00 $0.00
GLAZIER $30.00 $31.95 $61.95 Above median +115% vs market $0.00 $0.00 $0.00 $0.00
HAZARDOUS MATERIAL HANDLER $38.50 $25.04 $63.54 Above median $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL, ORNAMENTAL, RODMAN, MACHINERY MOVER, RIGGER, FENCE ERECTOR, REINFORCEMENT, AND STONE DERRICKMAN $35.50 $31.39 $66.89 Top 10% +46% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS: SHEETER (OTSEGO COUNTY) $38.75 $25.48 $64.23 +40% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS: SHEETER, BUCKER-UP (OTSEGO COUNTY) $38.75 $25.48 $64.23 +40% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS: STRUCTURAL, ORNAMENTAL, RODMAN, MACHINERY, MOVER, RIGGER, FENCE ERECTOR, REINFORCING, STONE DERRICKMEN (OTSEGO COUNTY) $38.50 $25.48 $63.98 +40% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 1: FLAGPERSON, GATEPERSON FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CH $38.40 $30.40 $68.80 +148% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 2: GENERAL LABORERS, CHUCK TENDER, HANDLING AND DISTRIBUTING DRINKING WATER, DISTRIBUTING ALL TOOLS AND SUPPLIES OF LABORERS, NIPPER $38.40 $30.40 $68.80 +148% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 3: INGERSOLL RAND HEAVY DUTY CRAWLER MASTER TYPE HCMZ, ANY DRILL USING 4"" OR LARGER BIT, ASBESTOS, TOXIC, BIO-REMEDIATION, PHYTO-REME $41.90 $30.40 $72.30 +161% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 4: ASBESTOS, TOXIC, LEAD OR HAZARDOUS MATERIAL ABATEMENT FOREMAN. FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDE $46.75 $30.40 $77.15 +178% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS $42.06 $30.59 $72.65 Above median +170% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, INCLUDING STEAMFITTING $44.91 $33.31 $78.22 Above median +107% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, INCLUDING STEAMFITTING $45.93 $33.77 $79.70 Top 10% +111% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER, AUTOMATIC FINE GRADER, BACKHOE, BACKHO $57.30 $33.55 $90.85 Top 10% +135% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE, BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT, BLAST OR ROTARY $56.39 $33.55 $89.94 Top 10% +133% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 $53.82 $33.55 $87.37 Top 10% +126% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANES FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DA $63.30 $33.55 $96.85 Top 10% +151% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THAN $61.80 $33.55 $95.35 Top 10% +147% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOW FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THA $60.30 $33.55 $93.85 Top 10% +143% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING $58.91 $33.55 $92.46 Top 10% +140% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $30.50 $19.84 $50.34 Above median +65% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $35.94 $20.89 $56.83 +61% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $47.85 $28.94 $76.79 Above median +104% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER GROUP 1 PICKUPS, PANEL TRUCKS, FLATBOY MATERIAL TRUCKS, SINGLE-AXLE DUMP TRUCKS, DUPSTERS, RECEIVERS, GREASERS, TRUCK TIREMEN, TANDEMS AN $35.48 $31.58 $67.06 +130% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER GROUP 2 SPECIALIZED EARTH MOVING EQUIPMENT-EUCLID TYPE, OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF LOADED,STRADDLE CARRIER, AND SEL $35.83 $31.58 $67.41 +132% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Otsego, NY — Heavy construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Otsego

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for NY20260037-16125-hvy →