Highway Construction — Oswego, New York

WD NY20260038-16124-hwy · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for BOILERMAKER in Oswego, New York (construction type: highway) is $35.23/hr base + $26.61/hr fringe = $61.84/hr total package (WD NY20260038-16124-hwy, Rev. 2).

Scroll down for all 57 trade classifications covered by this determination.

WD Number: NY20260038-16124-hwy
Revision: 2
Construction Type: highway
State: New York (NY)
County: Oswego
Effective: May 17, 2026
Trades covered: 57
Official source: SAM.gov reference NY20260038View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BOILERMAKER $35.23 $26.61 $61.84 +71% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER $34.15 $19.71 $53.86 +44% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $39.52 $27.16 $66.68 Above median +118% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR DAY, THANKSGIVING DAY $37.23 $19.51 $56.74 +87% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $50.50 $35.03 $85.53 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $55.55 $35.03 $90.58 Top 10% +143% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLU $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRID $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TR $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATIO $40.81 $6.99 $47.80 Top 10% +28% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DA $20.53 $6.39 $26.92 Top 10% -28% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NE $38.73 $6.93 $45.66 Top 10% +23% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $42.29 $30.66 $72.95 +96% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $52.86 $35.60 $88.46 Top 10% +138% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $47.57 $31.03 $78.60 Above median +111% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $31.72 $29.87 $61.59 Bottom 10% +65% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER $63.14 $33.82 $96.96 Top 10% +160% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid $64.59 $42.92 $107.51 Top 10% +189% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN $35.34 $30.12 $65.46 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or ga $35.34 $30.12 $65.46 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR $55.40 $31.78 $87.18 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail t $55.40 $31.78 $87.18 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type undergro $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type un $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or g $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RA $58.44 $38.44 $96.88 Above median +62% vs market $0.00 $0.00 $0.00 $0.00
FLOOR LAYER: CARPET $15.22 $2.09 $17.31 -38% vs market $0.00 $0.00 $0.00 $0.00
GLAZIER $30.00 $27.59 $57.59 Above median +100% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER $37.16 $30.68 $67.84 Above median +48% vs market $0.00 $0.00 $0.00 $0.00
LABORER $31.45 $23.10 $54.55 Above median +97% vs market $0.00 $0.00 $0.00 $0.00
LABORER $33.95 $23.10 $57.05 Above median +106% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 1 LABORERS, FLAGGERS, OUTBOARD AND HAND BOATS. FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, TH $36.30 $25.70 $62.00 +124% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 2 BULL FLOAT; CHAIN SAW, CONCRETE AGGREGATE BIN, CONCRETE BOOTMAN, GIN BUGGY, HAND OR MACHINE VIBRATOR, JACKHAMMER, MASON TENDER, MORTAR $36.50 $25.70 $62.20 +124% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 3 ALL ROCK OR DRILL MACHINE OPERATOR; ACETYLENE TORCH OPERATOR, ASPHALT RAKER, POWDERMAN. FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, ME $36.70 $25.70 $62.40 +125% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 4 BLASTER, FORM SETTERS, STONE OR GRANITE CURB SETTERS. FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABO $36.90 $25.70 $62.60 +126% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: BRIDGES $42.06 $30.59 $72.65 Top 10% +170% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: BRUSH & ROLL $29.90 $26.25 $56.15 Top 10% +109% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: PAPERHANGING, VINYL & TAPERS $30.90 $26.25 $57.15 +112% vs market $0.00 $0.00 $0.00 $0.00
PLASTERER $34.15 $19.71 $53.86 Above median +52% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, PIPEFITTER, STEAMFITTER $32.90 $23.61 $56.51 Bottom 10% +50% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER, AUTOMATIC FINE GRADER, BACKHOE, BACKHO $55.85 $33.40 $89.25 Bottom 10% +131% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE, BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT, BLAST OR ROTARY $54.97 $33.40 $88.37 Bottom 10% +129% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 $51.69 $33.40 $85.09 Top 10% +120% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANES FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DA $65.51 $33.40 $98.91 Top 10% +156% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVER FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, C $60.35 $33.40 $93.75 Top 10% +143% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOW FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY $58.85 $33.40 $92.25 Top 10% +139% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS $57.20 $33.40 $90.60 Top 10% +135% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $35.80 $25.99 $61.79 Above median +103% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER, INCL. HVAC DUCT $36.29 $23.31 $59.60 +69% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER, INCL. HVAC DUCT $42.29 $23.31 $65.60 +86% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $47.85 $28.94 $76.79 Above median +104% vs market $0.00 $0.00 $0.00 $0.00
THE TOWNSHIPS OF AMBOY, CONSTANTIA, ONEIDA LAKE AND PAINTERS: METALIZING $29.90 $26.25 $56.15 $0.00 $0.00 $0.00 $0.00
TILE FINISHER $26.46 $19.64 $46.10 Above median +52% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $32.92 $20.42 $53.34 Above median +76% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Oswego, NY — Highway construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Oswego

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for NY20260038-16124-hwy →