Highway Construction — Hamilton, New York

WD NY20260046-16120-hwy · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS WORKERS/INSULATOR in Hamilton, New York (construction type: highway) is $41.74/hr base + $27.58/hr fringe = $69.32/hr total package (WD NY20260046-16120-hwy, Rev. 2).

Scroll down for all 69 trade classifications covered by this determination.

WD Number: NY20260046-16120-hwy
Revision: 2
Construction Type: highway
State: New York (NY)
County: Hamilton
Effective: May 17, 2026
Trades covered: 69
Official source: SAM.gov reference NY20260046View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKERS/INSULATOR $41.74 $27.58 $69.32 Above median +127% vs market $0.00 $0.00 $0.00 $0.00
BOILERMAKER $43.34 $27.66 $71.00 +97% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER, CAULKER, CLEANER, POINTER, STONEMASON & CEMENT MASON FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR DAY, THANKGIVING DAY (P $33.82 $19.95 $53.77 +44% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $41.03 $24.50 $65.53 Above median +114% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER, HEAVY & HIGHWAY FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR DAY, THANKGIVING DAY (PROVIDED THE EMPLO $37.23 $19.51 $56.74 +87% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $48.00 $32.09 $80.09 Top 10% +115% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLU $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRID $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TR $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATIO $40.81 $6.99 $47.80 Top 10% +28% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DA $20.53 $6.39 $26.92 Top 10% -28% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NE $38.73 $6.93 $45.66 Top 10% +23% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $42.29 $30.66 $72.95 +96% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $52.86 $35.60 $88.46 Top 10% +138% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $47.57 $31.03 $78.60 Above median +111% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $31.72 $29.87 $61.59 Bottom 10% +65% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER $63.14 $33.82 $96.96 Top 10% +160% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid $64.59 $42.92 $107.51 Top 10% +189% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN $35.34 $30.12 $65.46 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or ga $35.34 $30.12 $65.46 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR $55.40 $31.78 $87.18 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail t $55.40 $31.78 $87.18 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type undergro $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type un $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or g $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
EMPLOYEE IS EMPLOYED DAY BEFORE AND DAY AFTER THE HOLIDAY.) $23.00 $20.64 $43.64 $0.00 $0.00 $0.00 $0.00
GLAZIER $37.25 $33.54 $70.79 Above median +145% vs market $0.00 $0.00 $0.00 $0.00
HAZARDOUS MATERIAL HANDLER $41.74 $27.58 $69.32 Above median $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL, ORNAMENTAL, RODMAN, MACHINERY MOVER, RIGGER, FENCE ERECTOR, REINFORCEMENT, AND STONE DERRICKMAN $35.50 $31.39 $66.89 Top 10% +46% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS: SHEETER $38.75 $25.48 $64.23 Bottom 10% +40% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS: STRUCTURAL, ORNAMENTAL, RODMAN, MACHINERY MOVER, RIGGER, FENCE ERECTOR, REINFORCING, STONE DERRICKMEN $38.50 $25.48 $63.98 +40% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS:: SHEETER, BUCKER-UP $38.75 $25.48 $64.23 +40% vs market $0.00 $0.00 $0.00 $0.00
LABORER BUILDING CONSTRUCTION FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY $24.00 $20.64 $44.64 +61% vs market $0.00 $0.00 $0.00 $0.00
LABORER BUILDING CONSTRUCTION: ASBESTOS REMOVAL FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY $24.00 $20.64 $44.64 +61% vs market $0.00 $0.00 $0.00 $0.00
LABORER BUILDING CONSTRUCTION: LABORERS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY AND CHR $22.50 $20.64 $43.14 +56% vs market $0.00 $0.00 $0.00 $0.00
LABORER BUILDING CONSTRUCTION: PIPELAYERS, MOTOR MIXERS, MOTOR BUGGY OPERATOR POWER LIFT FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR $22.65 $20.64 $43.29 +56% vs market $0.00 $0.00 $0.00 $0.00
LABORER BUILDING CONSTRUCTION: WAGON DRILL OPERATOR FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING $22.90 $20.64 $43.54 +57% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 1: COMMON LABORERS, FLAGMAN, OUTBOARD AND HAND BOATS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DA $28.05 $23.74 $51.79 +87% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 2: BULL FLOAT, CHAIN SAW, CONCRETE AGGREGATE BIN, CONCRETE BOOTMAN, GIN BUGGY, HAND OR MACHINE VIBRATOR, JACKHAMMER, MASON TENDER, MORTO $28.25 $23.74 $51.99 +87% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 3 ALL ROCK OR DRILLING MACHINE OPERATORS, ACETYLENE TORCH OPERATORS, AND ASPHALT PAVER, POWERMAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S $28.45 $23.74 $52.19 +88% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 4: BLASTERERS, FORM SETTERS, STONE OR GRANITE CURB SETTERS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LA $28.65 $23.74 $52.39 +89% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 5: HAZARDOUS WASTE REMOVAL FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY AND CH $24.00 $20.64 $44.64 +61% vs market $0.00 $0.00 $0.00 $0.00
MARBLE, TILE & TERRAZZO FINISHER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY AND CHRISTMAS $25.59 $16.34 $41.93 $0.00 $0.00 $0.00 $0.00
MARBLE, TILE LAYER & TERRAZZO WORKER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY AND CHRIST $32.59 $19.05 $51.64 $0.00 $0.00 $0.00 $0.00
PAINTERS $48.75 $35.63 $84.38 Top 10% +213% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: LEAD ABATEMENT WORKERS, STRUCTURAL STEEL $34.50 $21.69 $56.19 +109% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: PAINTERS, DRYWALL FINISHERS, SPRAY $33.50 $21.69 $55.19 Top 10% +105% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER AND STEAMFITTER $55.26 $29.12 $84.38 Above median +124% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER AND STEAMFITTER $45.88 $33.60 $79.48 Above median +111% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER: NORTHERN ZONE $45.93 $33.77 $79.70 +111% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER, AUTOMATIC FINE GRADER, BACKHOE, BACKHO $57.30 $33.55 $90.85 Top 10% +135% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE, BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT, BLAST OR ROTARY $56.39 $33.55 $89.94 Top 10% +133% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 $53.82 $33.55 $87.37 Top 10% +126% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANES FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DA $63.30 $33.55 $96.85 Top 10% +151% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THAN $61.80 $33.55 $95.35 Top 10% +147% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOW FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THA $60.30 $33.55 $93.85 Top 10% +143% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING $58.91 $33.55 $92.46 Top 10% +140% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP A CRANE, HYDRAULIC CRANES, TOWER CRANE, LOCOMOTIVE CRANE, PILEDRIVER, CABLEWAY, DERRICKS, WHIRLIES, DRAGLINE, BOOM TR $55.42 $33.20 $88.62 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP A SHOVEL, ALL EXCAVATORS, GRADALLS, POWER ROAD GRADER, ALL CMI EQUIPMENT, FRONT-END RUBBER TIRE LOADER, TRACTOR-MOUNT $54.93 $33.20 $88.13 +128% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP B BACKHOE,, BULLDOZER, PUSHCAT, TRACTOR, TRAXCAVATOR, SCRAPER, LETOURNEAU GRADER, FORM FINE GRADER, ROAD ROLLER, BLAC $53.91 $33.20 $87.11 +126% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP C FORK LIFT, HIGH LIFT, LULL, OILER, FIREMAN AND HEAVY- DUTY GREASER, BOILERS, AND STEAM GENERATORS, PUMP, VIBRATOR $51.01 $33.20 $84.21 +118% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $38.05 $24.27 $62.32 Above median +105% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. IF ANY OF THESE HO $33.73 $33.04 $66.77 +89% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $47.85 $28.94 $76.79 Above median +104% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 PICK-UPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS; SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN, TANDE $35.48 $31.58 $67.06 +130% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 SPECIALIZED EARTH MOVING EQUIPMENT- EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRAFFLE CARRIER; SELF $35.83 $31.58 $67.41 +132% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Hamilton, NY — Highway construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Hamilton

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for NY20260046-16120-hwy →