Highway Construction — Cortland, New York

WD NY20260042-16119-hwy · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for CARPENTER in Cortland, New York (construction type: highway) is $39.52/hr base + $27.16/hr fringe = $66.68/hr total package (WD NY20260042-16119-hwy, Rev. 2).

Scroll down for all 48 trade classifications covered by this determination.

WD Number: NY20260042-16119-hwy
Revision: 2
Construction Type: highway
State: New York (NY)
County: Cortland
Effective: May 17, 2026
Trades covered: 48
Official source: SAM.gov reference NY20260042View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
CARPENTER $39.52 $27.16 $66.68 Above median +118% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $38.63 $25.05 $63.68 Above median +110% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $50.50 $35.03 $85.53 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLU $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRID $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TR $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATIO $40.81 $6.99 $47.80 Top 10% +28% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DA $20.53 $6.39 $26.92 Top 10% -28% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NE $38.73 $6.93 $45.66 Top 10% +23% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $42.29 $30.66 $72.95 +96% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $52.86 $35.60 $88.46 Top 10% +138% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $47.57 $31.03 $78.60 Above median +111% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $31.72 $29.87 $61.59 Bottom 10% +65% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER $63.14 $33.82 $96.96 Top 10% +160% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid $64.59 $42.92 $107.51 Top 10% +189% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN $35.34 $30.12 $65.46 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or ga $35.34 $30.12 $65.46 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR $55.40 $31.78 $87.18 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail t $55.40 $31.78 $87.18 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type undergro $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type un $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or g $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RA $58.44 $38.44 $96.88 Above median +62% vs market $0.00 $0.00 $0.00 $0.00
GLAZIER $30.00 $27.59 $57.59 Above median +100% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER $37.16 $30.68 $67.84 Above median +48% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 1 LABORERS; FLAGGERS; OUTBOARD AND HAND BOATS $35.56 $25.60 $61.16 +121% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 2 BULL FLOAT; CHAIN SAW; CONCRETE AGGREGATE BIN; CONCRETE BOOTMAN; GIN BUGGY; HAND OR MACHINE VIBRATOR; JACKHAMMER; MASON TENDER; MORTA $35.76 $25.60 $61.36 +121% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 3 ALL ROCK OR DRILL MACHINE OPERATORS; ACETYLENE TORCH OPERATOR; ASPHALT RAKER; POWDERMAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; M $35.96 $25.60 $61.56 +122% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 4 BLASTERS; FORM SETTERS; STONE OR GRANITE CURB SETTERS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAB $36.16 $25.60 $61.76 +123% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 5 HAZARDOUS WASTE REMOVAL FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRI $38.76 $25.60 $64.36 +132% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, PIPEFITTER, STEAMFITTER: INCLUDING HVAC WORK $35.51 $24.57 $60.08 Top 10% +59% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER: SOUTHERN ZONE $44.91 $33.31 $78.22 +107% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER, AUTOMATIC FINE GRADER, BACKHOE, BACKHO $55.85 $33.40 $89.25 Bottom 10% +131% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE, BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT, BLAST OR ROTARY $54.97 $33.40 $88.37 Bottom 10% +129% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 $51.69 $33.40 $85.09 Top 10% +120% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANES FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DA $65.51 $33.40 $98.91 Top 10% +156% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVER FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, C $60.35 $33.40 $93.75 Top 10% +143% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOW FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY $58.85 $33.40 $92.25 Top 10% +139% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS $57.20 $33.40 $90.60 Top 10% +135% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $35.80 $25.99 $61.79 Above median +103% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $46.29 $23.31 $69.60 Above median +97% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $36.29 $23.31 $59.60 +69% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $47.85 $28.94 $76.79 Above median +104% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER GROUP 1 YARDMAN; PICKUPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS; SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN $35.48 $31.58 $67.06 +130% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER GROUP 2 SPECIALIZED EARTH MOVING EQUIPMENT - EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRADDLE CARRIER; SELF $35.83 $31.58 $67.41 +132% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Cortland, NY — Highway construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.