Highway Construction — Churchill, Nevada

WD NV20260046-17480-hwy · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for CEMENT MASON/CONCRETE FINISHER in Churchill, Nevada (construction type: highway) is $37.67/hr base + $16.98/hr fringe = $54.65/hr total package (WD NV20260046-17480-hwy, Rev. 2).

Scroll down for all 26 trade classifications covered by this determination.

WD Number: NV20260046-17480-hwy
Revision: 2
Construction Type: highway
State: Nevada (NV)
County: Churchill
Effective: May 17, 2026
Trades covered: 26
Official source: SAM.gov reference NV20260046View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
CEMENT MASON/CONCRETE FINISHER $37.67 $16.98 $54.65 Above median +88% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, REINFORCING $50.70 $35.15 $85.85 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR $34.45 $16.30 $50.75 Top 10% +121% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $33.95 $16.30 $50.25 Top 10% +119% vs market $0.00 $0.00 $0.00 $0.00
LABORER: CONCRETE SAW $34.20 $16.30 $50.50 Above median +120% vs market $0.00 $0.00 $0.00 $0.00
LABORER: JACKHAMMER $34.20 $16.30 $50.50 Above median +120% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - CEMENT/CONCRETE $34.20 $16.30 $50.50 Top 10% +120% vs market $0.00 $0.00 $0.00 $0.00
LABORER: PIPELAYER $34.45 $16.30 $50.75 Top 10% +121% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: ASPHALT/CONCRETE LAYDOWN $60.39 $30.38 $90.77 $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $40.38 $22.61 $62.99 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $36.47 $24.06 $60.53 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: BROOM/SWEEPER $44.42 $19.21 $63.63 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: BULLDOZER $60.39 $30.38 $90.77 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: DRILL $46.92 $25.02 $71.94 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: GRADER/BLADE $50.47 $30.38 $80.85 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $49.61 $30.38 $79.99 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: MECHANIC $35.90 $23.95 $59.85 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: MILLING MACHINE $55.93 $15.47 $71.40 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: OILER $63.57 $36.40 $99.97 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: PAVER $36.85 $25.26 $62.11 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: ROLLER $60.39 $30.38 $90.77 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: SCREED $43.24 $25.09 $68.33 Top 10% $0.00 $0.00 $0.00 $0.00
TRAFFIC CONTROL: FLAGGER $32.08 $16.30 $48.38 Top 10% $0.00 $0.00 $0.00 $0.00
TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER $30.23 $11.02 $41.25 Above median $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $40.52 $0.00 $40.52 Top 10% +38% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: WATER TRUCK $42.48 $0.00 $42.48 Top 10% +45% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Churchill, NV — Highway construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Churchill

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for NV20260046-17480-hwy →