Highway Construction — Seward, Nebraska

WD NE20260027-15966-hwy · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for CARPENTER in Seward, Nebraska (construction type: highway) is $18.51/hr base + $0.00/hr fringe = $18.51/hr total package (WD NE20260027-15966-hwy, Rev. 1).

Scroll down for all 57 trade classifications covered by this determination.

WD Number: NE20260027-15966-hwy
Revision: 1
Construction Type: highway
State: Nebraska (NE)
County: Seward
Effective: May 17, 2026
Trades covered: 57
Official source: SAM.gov reference NE20260027View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
CARPENTER $18.51 $0.00 $18.51 -22% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $18.17 $5.86 $24.03 +4% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $18.48 $5.86 $24.34 +5% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN) $46.40 $20.89 $67.29 +133% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, INCLUDES INSTALLATION OF TRAFFIC SIGNALS $28.83 $0.00 $28.83 Above median +0% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS:. REMAINDER OF SAUNDERS COUNTY ZONE 1: 0 TO 35 MILES [MILEAGE FROM MAIN POST OFFICE IN LINCOLN] FOOTNOTE: WORK ON SCAFFOLDS, HANGING SCAF $35.00 $18.88 $53.88 +87% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS:. REMAINDER OF SAUNDERS COUNTY ZONE 1: 36 TO 50 MILES [MILEAGE FROM MAIN POST OFFICE IN LINCOLN] FOOTNOTE: WORK ON SCAFFOLDS, HANGING SCA $35.30 $18.91 $54.21 +88% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS:. REMAINDER OF SAUNDERS COUNTY ZONE 3: 51 TO 75 MILES [MILEAGE FROM MAIN POST OFFICE IN LINCOLN] FOOTNOTE: WORK ON SCAFFOLDS, HANGING SCA $35.60 $18.94 $54.54 +89% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS:. REMAINDER OF SAUNDERS COUNTY ZONE 4: 76 MILES AND OVER [MILEAGE FROM MAIN POST OFFICE IN LINCOLN] FOOTNOTE: WORK ON SCAFFOLDS, HANGING $36.00 $18.99 $54.99 +91% vs market $0.00 $0.00 $0.00 $0.00
HIGHWAY/PARKING LOT STRIPING: LABORER $11.27 $0.00 $11.27 $0.00 $0.00 $0.00 $0.00
HIGHWAY/PARKING LOT STRIPING: LABORER $12.37 $0.00 $12.37 Above median $0.00 $0.00 $0.00 $0.00
HIGHWAY/PARKING LOT STRIPING: LABORER $11.82 $0.00 $11.82 $0.00 $0.00 $0.00 $0.00
IRONWORKER, REINFORCING $19.35 $0.00 $19.35 -35% vs market $0.00 $0.00 $0.00 $0.00
LABORER, COMMON OR GENERAL $12.20 $0.00 $12.20 Top 10% -46% vs market $0.00 $0.00 $0.00 $0.00
LABORER, COMMON OR GENERAL $12.55 $0.00 $12.55 Top 10% -44% vs market $0.00 $0.00 $0.00 $0.00
LABORER, COMMON OR GENERAL $12.58 $0.00 $12.58 Top 10% -44% vs market $0.00 $0.00 $0.00 $0.00
LABORER: CONCRETE SAW $16.07 $6.55 $22.62 +1% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER $10.44 $0.00 $10.44 Above median -54% vs market $0.00 $0.00 $0.00 $0.00
LABORER: TRAFFIC CONTROL - FLAGGER AND CONE/BARREL SETTER $9.00 $0.00 $9.00 Bottom 10% -60% vs market $0.00 $0.00 $0.00 $0.00
LABORER: TRAFFIC CONTROL - FLAGGER AND CONE/BARREL SETTER $11.87 $0.00 $11.87 Above median -47% vs market $0.00 $0.00 $0.00 $0.00
OPERATING ENGINEERS:, SKID LOADER $14.85 $0.00 $14.85 -46% vs market $0.00 $0.00 $0.00 $0.00
OPERATING ENGINEERS:, SKID LOADER.$ 12.51 0.00 OPERATING ENGINEERS:, SKID LOADER $10.56 $0.00 $10.56 -62% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: ASPHALT SPREADER $18.74 $0.00 $18.74 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE LOADER COMBO $15.94 $0.00 $15.94 $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR $16.15 $0.00 $16.15 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR $19.47 $6.07 $25.54 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR $19.91 $6.07 $25.98 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BROOM/SWEEPER $11.43 $0.00 $11.43 $0.00 $0.00 $0.00 $0.00
OPERATOR: BULLDOZER $16.34 $0.00 $16.34 $0.00 $0.00 $0.00 $0.00
OPERATOR: BULLDOZER $16.78 $0.00 $16.78 $0.00 $0.00 $0.00 $0.00
OPERATOR: COMPACTOR $13.36 $0.00 $13.36 $0.00 $0.00 $0.00 $0.00
OPERATOR: CONCRETE SAW $20.87 $0.00 $20.87 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: CRANE $22.38 $0.00 $22.38 $0.00 $0.00 $0.00 $0.00
OPERATOR: GRADER/BLADE..$ 16.04 0.00 OPERATOR: GRADER/BLADE $16.09 $0.00 $16.09 $0.00 $0.00 $0.00 $0.00
OPERATOR: HYDROHAMMER $17.03 $0.00 $17.03 $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $16.04 $0.00 $16.04 $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $17.19 $0.00 $17.19 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $17.44 $0.00 $17.44 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: MECHANIC $19.58 $0.00 $19.58 $0.00 $0.00 $0.00 $0.00
OPERATOR: MILLING MACHINE $12.80 $0.00 $12.80 Bottom 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: OILER $16.21 $0.00 $16.21 $0.00 $0.00 $0.00 $0.00
OPERATOR: PAVER $16.13 $0.00 $16.13 $0.00 $0.00 $0.00 $0.00
OPERATOR: PAVER $14.79 $0.00 $14.79 $0.00 $0.00 $0.00 $0.00
OPERATOR: ROLLER $14.04 $0.00 $14.04 $0.00 $0.00 $0.00 $0.00
OPERATOR: ROLLER $13.45 $0.00 $13.45 $0.00 $0.00 $0.00 $0.00
OPERATOR: ROLLER $13.00 $0.00 $13.00 $0.00 $0.00 $0.00 $0.00
OPERATOR: SCRAPER $14.83 $0.00 $14.83 $0.00 $0.00 $0.00 $0.00
OPERATOR: SCRAPER $14.80 $0.00 $14.80 $0.00 $0.00 $0.00 $0.00
OPERATOR: TRACTOR $10.65 $0.00 $10.65 $0.00 $0.00 $0.00 $0.00
OPERATOR: TRACTOR $9.50 $0.00 $9.50 Bottom 10% $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK $14.16 $0.00 $14.16 Above median -49% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK $14.47 $0.00 $14.47 Above median -48% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK $14.51 $0.00 $14.51 Above median -48% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: LOWBOY TRUCK $15.93 $0.00 $15.93 -43% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: SEMI-TRAILER TRUCK $14.09 $0.00 $14.09 Above median -49% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: SEMI-TRAILER TRUCK $13.48 $0.00 $13.48 Above median -52% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: WATER TRUCK $18.00 $6.40 $24.40 Above median -12% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Seward, NE — Highway construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Seward

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for NE20260027-15966-hwy →