Building Construction — Dixon, Nebraska

WD NE20260063-16003-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for BRICKLAYER in Dixon, Nebraska (construction type: building) is $34.80/hr base + $19.94/hr fringe = $54.74/hr total package (WD NE20260063-16003-bld, Rev. 1).

Scroll down for all 20 trade classifications covered by this determination.

WD Number: NE20260063-16003-bld
Revision: 1
Construction Type: building
State: Nebraska (NE)
County: Dixon
Effective: May 17, 2026
Trades covered: 20
Official source: SAM.gov reference NE20260063View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BRICKLAYER $34.80 $19.94 $54.74 Above median +90% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $33.42 $18.66 $52.08 +118% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $21.32 $5.97 $27.29 +14% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $17.74 $3.50 $21.24 -8% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $40.68 $19.70 $60.38 Above median +109% vs market $0.00 $0.00 $0.00 $0.00
FORM WORKER $18.18 $3.65 $21.83 Above median $0.00 $0.00 $0.00 $0.00
IRONWORKER, STRUCTURAL $32.14 $19.28 $51.42 Above median +72% vs market $0.00 $0.00 $0.00 $0.00
LABORER $24.00 $13.48 $37.48 +67% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $14.23 $4.43 $18.66 Above median -17% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $20.68 $4.93 $25.61 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $21.72 $2.10 $23.82 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: CRANE $36.44 $18.69 $55.13 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: FORKLIFT $31.06 $18.69 $49.75 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $19.27 $4.00 $23.27 Above median $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER AND SPRAY $14.26 $0.00 $14.26 -34% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER $43.20 $23.25 $66.45 Above median +120% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $43.20 $23.25 $66.45 Above median +120% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $13.57 $0.77 $14.34 -35% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $39.65 $19.87 $59.52 +111% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK $14.09 $2.49 $16.58 Above median -40% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Dixon, NE — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Dixon

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for NE20260063-16003-bld →