Building Construction — Garfield, Montana

WD MT20260057-17741-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for 31 TO 60 MILES - $4.00 ZONE 3: OVER 60 MILES - $6.00 in Garfield, Montana (construction type: building) is $32.05/hr base + $15.02/hr fringe = $47.07/hr total package (WD MT20260057-17741-bld, Rev. 1).

Scroll down for all 28 trade classifications covered by this determination.

WD Number: MT20260057-17741-bld
Revision: 1
Construction Type: building
State: Montana (MT)
County: Garfield
Effective: May 17, 2026
Trades covered: 28
Official source: SAM.gov reference MT20260057View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
31 TO 60 MILES - $4.00 ZONE 3: OVER 60 MILES - $6.00 $32.05 $15.02 $47.07 Top 10% $0.00 $0.00 $0.00 $0.00
60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 $42.00 $16.20 $58.20 Above median $0.00 $0.00 $0.00 $0.00
60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 $38.00 $16.20 $54.20 $0.00 $0.00 $0.00 $0.00
60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 $21.51 $16.20 $37.71 $0.00 $0.00 $0.00 $0.00
BOILERMAKER $38.75 $32.31 $71.06 +78% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER $30.55 $15.75 $46.30 +48% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER, EXCLUDES DRYWALL HANGING, AND FORM WORK..$ 16.70 2.31 CARPENTER $22.69 $0.00 $22.69 Top 10% -19% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $18.27 $1.50 $19.77 -26% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $40.42 $18.34 $58.76 +77% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $43.92 $18.17 $62.09 Above median +87% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTE: ADDITIONAL FRINGE BENEFITS DUE A. EMPLOYER CONTRIBUTES 8% OF THE BASIC HOURLY RATE FOR OVER 5 YEAR'S SERVICE AND 6% OF THE $67.61 $38.44 $106.05 +161% vs market $0.00 $0.00 $0.00 $0.00
HEAT AND FROST INSULATOR $43.81 $21.87 $65.68 Top 10% $0.00 $0.00 $0.00 $0.00
IRONWORKER, REINFORCING $36.83 $25.30 $62.13 Above median +130% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, STRUCTURAL $20.45 $12.76 $33.21 +23% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $14.47 $3.11 $17.58 Above median -26% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - BRICK $18.37 $5.94 $24.31 Above median +3% vs market $0.00 $0.00 $0.00 $0.00
MILLWRIGHT ZONE DEFINITION: THE HOURLY RATE APPLICABLE TO EACH PROJECT IS DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL ROUTE FRO $46.21 $23.50 $69.71 Top 10% +142% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: EXCAVATOR $22.98 $5.57 $28.55 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: FORKLIFT $21.44 $8.05 $29.49 Above median $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER AND SPRAY $19.18 $0.00 $19.18 Above median -18% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER, EXCLUDES HVAC PIPE INSTALLATION $44.35 $21.87 $66.22 Above median +77% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $25.75 $10.87 $36.62 -2% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION $41.00 $20.47 $61.47 Above median +64% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER/PIPEFITTER: EXCLUDING HVAC PIPE INSTALLATION $46.45 $19.92 $66.37 +77% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: CRANES 75 TO 144 TONS, WHIRLEY CRANES ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EAC $40.00 $16.20 $56.20 Top 10% +94% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $17.36 $3.83 $21.19 -10% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $40.00 $22.07 $62.07 Above median +108% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $18.88 $4.66 $23.54 Above median -17% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Garfield, MT — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Garfield

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MT20260057-17741-bld →