Building Construction — Maries, Missouri
WD MO20260033-15889-bld · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for ASBESTOS WORKER/HEAT & FROST INSULATOR in Maries, Missouri (construction type: building) is $43.48/hr base + $27.24/hr fringe = $70.72/hr total package (WD MO20260033-15889-bld, Rev. 1).
Scroll down for all 50 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $43.48 | $27.24 | $70.72 Above median +196% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $31.97 | $14.00 | $45.97 +92% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $27.66 | $5.88 | $33.54 -1% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER, INCLUDING DRYWALL HANGING & FORM WORK | $39.53 | $21.85 | $61.38 Bottom 10% +109% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER, INCLUDING DRYWALL HANGING & FORM WORK | $41.30 | $21.85 | $63.15 Top 10% +115% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER: INCLUDING DRYWALL HANGING & FORM WORK | $44.19 | $21.85 | $66.04 +125% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER: INCLUDING DRYWALL HANGING, FORM WORK & RESILIENT/VINYL FLOOR INSTALLATION | $31.51 | $22.25 | $53.76 +83% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER: RESILIENT & VINYL FLOORING ONLY | $40.08 | $21.85 | $61.93 +111% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $33.52 | $15.88 | $49.40 Above median +80% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $36.63 | $9.85 | $46.48 Above median +69% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $54.01 | $27.85 | $81.86 Top 10% +140% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $40.50 | $23.26 | $63.76 Above median +87% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $37.60 | $22.14 | $59.74 +75% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| GLAZIER | $29.87 | $1.47 | $31.34 +34% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, REINFORCING | $21.02 | $9.49 | $30.51 Above median +5% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, STRUCTURAL | $36.00 | $34.25 | $70.25 Top 10% +143% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, STRUCTURAL | $41.67 | $31.25 | $72.92 Top 10% +152% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: ASBESTOS ABATEMENT | $24.90 | $0.00 | $24.90 -4% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: BRICK MASON TENDER | $28.95 | $14.95 | $43.90 +70% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: BRICK MASON TENDER | $32.23 | $15.91 | $48.14 Above median +86% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: BRICK MASON TENDER | $29.71 | $15.50 | $45.21 +75% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL & LANDSCAPE | $26.95 | $14.95 | $41.90 +62% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL & LANDSCAPE | $30.33 | $15.91 | $46.24 Above median +79% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL & LANDSCAPE | $27.71 | $15.50 | $43.21 +67% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL, LANDSCAPE & BRICK MASON TENDER | $41.18 | $15.96 | $57.14 +121% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH & ROLLER ONLY | $24.43 | $17.76 | $42.19 Bottom 10% +75% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH & ROLLER ONLY | $33.90 | $17.21 | $51.11 Above median +112% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH, ROLLER, & DRYWALL FINISHING/TAPING ONLY | $28.56 | $17.21 | $45.77 +90% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: DRYWALL FINISHING/TAPING ONLY | $25.39 | $17.76 | $43.15 +79% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: DRYWALL FINISHING/TAPING ONLY | $34.90 | $17.21 | $52.11 Above median +116% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: SPRAY | $18.79 | $8.12 | $26.91 +12% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION | $57.51 | $28.35 | $85.86 Top 10% +188% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER | $48.66 | $30.13 | $78.79 Top 10% +164% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION | $50.60 | $29.38 | $79.98 Bottom 10% +168% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION | $58.38 | $25.29 | $83.67 Top 10% +180% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER | $48.66 | $30.13 | $78.79 Top 10% +164% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION | $50.60 | $29.38 | $79.98 Bottom 10% +168% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR | $39.06 | $30.38 | $69.44 Top 10% +141% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: BULLDOZER | $39.06 | $30.38 | $69.44 Above median +141% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE | $39.06 | $30.38 | $69.44 Top 10% +141% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: ROLLER | $35.76 | $30.38 | $66.14 Above median +129% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $33.60 | $19.99 | $53.59 Above median +109% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $40.00 | $22.05 | $62.05 Above median +142% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $32.25 | $17.46 | $49.71 Above median +93% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $47.20 | $26.28 | $73.48 Above median +130% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $52.00 | $27.12 | $79.12 Top 10% +148% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $36.51 | $22.39 | $58.90 Above median +85% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $45.94 | $27.53 | $73.47 Above median +146% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE SETTER | $32.79 | $21.31 | $54.10 Above median +86% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $25.57 | $0.00 | $25.57 Above median +5% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Maries, MO — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Maries
Compliance Notes
- This wage determination applies to federal contracts for building construction in Maries, Missouri.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.