Heavy Construction — Johnson, Missouri

WD MO20260001-15722-hvy · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for CARPENTER AND PILEDRIVER in Johnson, Missouri (construction type: heavy) is $38.04/hr base + $22.40/hr fringe = $60.44/hr total package (WD MO20260001-15722-hvy, Rev. 2).

Scroll down for all 165 trade classifications covered by this determination.

WD Number: MO20260001-15722-hvy
Revision: 2
Construction Type: heavy
State: Missouri (MO)
County: Johnson
Effective: May 17, 2026
Trades covered: 165
Official source: SAM.gov reference MO20260001View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
CARPENTER AND PILEDRIVER $38.04 $22.40 $60.44 Above median +106% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER AND PILEDRIVER $36.13 $22.40 $58.53 Above median +99% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER AND PILEDRIVER $42.19 $22.40 $64.59 Top 10% +120% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER AND PILEDRIVER $35.37 $22.40 $57.77 Above median +96% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER AND PILEDRIVER $34.04 $22.40 $56.44 +92% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER AND PILEDRIVER $34.98 $22.40 $57.38 +95% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER AND PILEDRIVER $33.25 $22.40 $55.65 Bottom 10% +89% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER AND PILEDRIVER (AUDRAIN, RALLS, MARION, LEWIS, CLARK AND SCOTLAND COUNTIES)..$ 35.61 22.40 CARPENTER AND PILEDRIVER $34.98 $22.40 $57.38 Top 10% +95% vs market $0.00 $0.00 $0.00 $0.00
CARPENTERS $41.71 $21.85 $63.56 Above median +116% vs market $0.00 $0.00 $0.00 $0.00
CARPENTERS: CARPENTERS & LATHERS (CASS, CLAY, JACKSON, PLATTE AND RAY COUNTIES) $44.63 $22.40 $67.03 Top 10% +128% vs market $0.00 $0.00 $0.00 $0.00
CARPENTERS: MILLWRIGHTS & PILEDRIVERS (CASS, CLAY, JACKSON, PLATTE AND RAY COUNTIES) $44.63 $22.40 $67.03 Top 10% +84% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON $37.29 $20.23 $57.52 Above median +110% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON $32.00 $19.72 $51.72 +89% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON $35.10 $18.78 $53.88 Above median +96% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON (JEFFERSON, ST. CHARLES COUNTIES AND ST.LOUIS) $38.46 $20.13 $58.59 Top 10% +114% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $30.37 $12.43 $42.80 Above median +56% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $33.52 $15.88 $49.40 Above median +80% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASONS: (CASS, CLAY, JACKSON, PLATTE AND RAY COUNTIES) $39.06 $18.71 $57.77 Top 10% +111% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS $54.01 $27.85 $81.86 Top 10% +140% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS $28.65 $18.34 $46.99 Bottom 10% +38% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS $39.70 $19.84 $59.54 +75% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS $32.40 $19.11 $51.51 +51% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS $43.20 $21.50 $64.70 Above median +90% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS (ADAIR, AUDRAIN, CLARK, KNOX, LEWIS, LINN, MACON, MARION, MONROE, MONTGOMERY, PIKE, PUTNAM, RALLS, SCHUYLER, SCOTLAND, SHELBY AND SULLIVA $37.60 $22.14 $59.74 Top 10% +75% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS (BOLLINGER, BUTLER, CAPE GIRARDEAU, CARTER, DUNKLIN, FRANKLIN, IRON, JEFFERSON, LINCOLN, MADISON, MISSISSIPPI, NEW MADRID, PEMISCOT, PERR $49.29 $33.64 $82.93 Top 10% +143% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS: ELECTRICIANS $32.25 $20.81 $53.06 Top 10% +56% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS:: ELECTRICIANS (AUDRAIN, BOONE, CALLAWAY, CAMDEN, CHARITON, COLE, CRAWFORD, DENT, GASCONADE, HOWARD, MARIES, MILLER, MONITEAU, OSAGE, PHE $40.50 $23.26 $63.76 Top 10% +87% vs market $0.00 $0.00 $0.00 $0.00
HOWARD, KNOX,LINN, MACON, MILLER, MONITEAU,MONROE, OSAGE, PUTNAM, RANDOLPH, SCHUYLER, SHELBY AND SULLIVAN COUNTIES) $35.61 $22.40 $58.01 Top 10% $0.00 $0.00 $0.00 $0.00
IRONWORKER $27.00 $20.96 $47.96 +66% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER $41.67 $31.25 $72.92 Above median +152% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER $36.30 $25.80 $62.10 +114% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER (ST. LOUIS, ST. CHARLES, JEFFERSON, IRON, FRANKLIN, LINCOLN, WARREN, WASHINGTON, ST. FRANCOIS, STE. GENEVIEVE, AND REYNOLDS COUNTIES; AND P $44.27 $31.65 $75.92 Top 10% +162% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS $39.00 $34.25 $73.25 Top 10% +153% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS $36.00 $34.25 $70.25 Above median +143% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS:: ALL OTHER WORK $33.47 $24.12 $57.59 Top 10% +99% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS:: LOCKS, DAMS, BRIDGES AND OTHER MAJOR WORK ON THE MISSISSIPPI AND OHIO RIVER ONLY $38.77 $29.51 $68.28 Top 10% +136% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 1 GENERAL LABORER-FLAGMAN, CARPENTER TENDERS; SALAMANDER TENDERS; DUMP MAN; TICKET TAKERS; LOADING TRUCKS UNDER BINS, HOPPERS, AND CONVE $37.25 $15.96 $53.21 Top 10% +106% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 1 GENERAL LABORERS, CARPENTER TENDERS, SALAMANDER TENDERS, LOADING TRUCKS UNDER BINS, HOPPERS AND CONVEYORS, TRACK MEN AND ALL OTHER GEN $36.24 $15.87 $52.11 Top 10% +101% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 2 SKILLED LABORER - SPREADER OR SCREED MAN ON ASPHALT MACHINE, ASPHALT RAKER, GRADE CHECKER, VIBRATOR MAN, CONCRETE SAW OVER 5 HP., LASE $37.45 $15.87 $53.32 Top 10% +106% vs market $0.00 $0.00 $0.00 $0.00
LABORER, COMMON OR GENERAL: LINCOLN, MONNTOMERY, AND WARRNER COUNTIES $39.76 $15.96 $55.72 Top 10% +115% vs market $0.00 $0.00 $0.00 $0.00
LABORER, COMMON OR GENERAL: ST. CHARLES COUNTY $41.18 $15.96 $57.14 Top 10% +121% vs market $0.00 $0.00 $0.00 $0.00
LABORER, GROUP 1 GENERAL LABORERS - CARPENTER TENDERS; SALAMANDER TENDERS; LOADING TRUCKS UNDER BINS; HOPPERS & CONVEYORS; TRACK MEN & ALL OTHER GENER $28.23 $15.60 $43.83 Bottom 10% +69% vs market $0.00 $0.00 $0.00 $0.00
LABORER, GROUP 1 GENERAL LABORERS - CARPENTER TENDERS; SALAMANDER TENDERS; LOADING TRUCKS UNDER BINS; HOPPERS & CONVEYORS; TRACK MEN & ALL OTHER GENER $29.04 $16.59 $45.63 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
LABORER: DYNAMITER, POWDERMAN (ST. LOUIS) $40.82 $17.56 $58.38 Top 10% +125% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 1 GENERAL LABORER-FLAGMAN, CARPENTER TENDERS; SALAMANDER TENDERS; DUMP MAN; TICKET TAKERS; LOADING TRUCKS UNDER BINS, HOPPERS, AND CONV $40.36 $15.96 $56.32 Top 10% +118% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 1 GENERAL LABORER-FLAGMAN, CARPENTER TENDERS; SALAMANDER TENDERS; DUMP MAN; TICKET TAKERS; LOADING TRUCKS UNDER BINS, HOPPERS, AND CONV $37.25 $15.96 $53.21 Bottom 10% +106% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 1 GENERAL LABORER-FLAGMAN, CARPENTER TENDERS; SALAMANDER TENDERS; DUMP MAN; TICKET TAKERS; LOADING TRUCKS UNDER BINS, HOPPERS, AND CONV $40.31 $15.96 $56.27 Above median +117% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 1 GENERAL LABORERS - CARPENTER TENDERS; SALAMANDER TENDERS; LOADING TRUCKS UNDER BINS; HOPPERS & CONVEYORS; TRACK MEN & ALL OTHER GENER $29.39 $16.59 $45.98 Top 10% +78% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 2 SKILLED LABORERS - HEAD PIPE LAYER ON SEWER WORK; LASER BEAM MAN; JACKSON OR ANY OTHER SIMILAR TAMP; CUTTING TORCH MAN; FORM SETTERS $30.13 $15.85 $45.98 Top 10% +78% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LABORERS, FLAGGERS (ST. LOUIS) $40.82 $17.56 $58.38 Top 10% +125% vs market $0.00 $0.00 $0.00 $0.00
LABORER: PLUMBER LABORER (ST. LOUIS) $40.82 $17.56 $58.38 Top 10% +125% vs market $0.00 $0.00 $0.00 $0.00
LABORER: WRECKING (ST. LOUIS) $40.82 $17.56 $58.38 Top 10% +125% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN $35.86 $25.88 $61.74 Top 10% +37% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN POWDERMAN $38.44 $20.76 $59.20 Top 10% +32% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: LINEMAN $58.15 $27.56 $85.71 Above median +91% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: LINEMAN OPERATOR $52.45 $20.13 $72.58 Top 10% +61% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION:: EQUIPMENT OPERATOR (ADAIR, AUDRAIN, BOONE, CALLAWAY, CAMDEN, CARTER, CHARITON, CLARK, COLE, COOPER, CRAWFORD, DENT, FRANKLIN, GASC $49.68 $25.63 $75.31 Top 10% +67% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION:: GROUNDMAN & TRUCK DRIVER (ADAIR, AUDRAIN, BOONE, CALLAWAY, CAMDEN, CARTER, CHARITON, CLARK, COLE, COOPER, CRAWFORD, DENT, FRAN $37.95 $21.35 $59.30 Top 10% +32% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION:: GROUNDMAN - CLASS A $38.18 $19.92 $58.10 Top 10% +29% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION:: GROUNDMAN-EQUIPMENT OPERATOR CLASS II $46.49 $22.33 $68.82 Top 10% +53% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION:: HEAVY-EQUIPMENT OPERATOR CLASS I $52.13 $23.97 $76.10 Top 10% +69% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION:: LINEMAN $74.55 $30.47 $105.02 Top 10% +133% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION:: LINEMAN & CABLE SPLICER (ADAIR, AUDRAIN, BOONE, CALLAWAY, CAMDEN, CARTER, CHARITON, CLARK, COLE, COOPER, CRAWFORD, DENT, FRANK $57.88 $28.63 $86.51 Top 10% +92% vs market $0.00 $0.00 $0.00 $0.00
ON ELECTRONIC GRADE CONTROL; MANHOLE BUILDER; DYNAMITE MAN; POWDER MAN; WELDER; TUNNEL MAN; WATERBLASTER - 1000 PSI OR OVER; ASBESTOS AND/OR HAZARDOUS $40.36 $15.96 $56.32 Top 10% $0.00 $0.00 $0.00 $0.00
ON ELECTRONIC GRADE CONTROL; MANHOLE BUILDER; DYNAMITE MAN; POWDER MAN; WELDER; TUNNEL MAN; WATERBLASTER - 1000 PSI OR OVER; ASBESTOS AND/OR HAZARDOUS $37.25 $15.96 $53.21 Bottom 10% $0.00 $0.00 $0.00 $0.00
ON ELECTRONIC GRADE CONTROL; MANHOLE BUILDER; DYNAMITE MAN; POWDER MAN; WELDER; TUNNEL MAN; WATERBLASTER - 1000 PSI OR OVER; ASBESTOS AND/OR HAZARDOUS $40.31 $15.96 $56.27 Above median $0.00 $0.00 $0.00 $0.00
PAINTERS: BRIDGES, STACKS & TANKS. HEIGHT RATES: 0VER 60 FT. $0.50 PER HOUR UNDER 60 FT. $0.25 PER HOUR $36.53 $17.92 $54.45 Top 10% +126% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: BRUSH & ROLLER $24.43 $17.76 $42.19 Bottom 10% +75% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: BRUSH & ROLLER $36.18 $19.97 $56.15 Above median +133% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: BRUSH & ROLLER. HEIGHT RATES: 0VER 60 FT. $0.50 PER HOUR UNDER 60 FT. $0.25 PER HOUR $30.95 $17.92 $48.87 Top 10% +103% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: BRUSH & ROLLER.$ 30.54 17.76 PAINTERS: BRIDGEMAN; LEAD ABATEMENT; SANDBLAST; STORAGE BIN & TANKS $33.41 $17.76 $51.17 Top 10% +112% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: BRUSH AND ROLLER $33.90 $17.21 $51.11 Bottom 10% +112% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: BRUSH AND ROLLER; TAPER (CLARK, FRANKLIN, JEFFERSON, LEWIS, LINCOLN, MARION, PIKE, RALLS, ST. CHARLES, ST. LOUIS, AND WARREN COUNTIES) $28.61 $10.24 $38.85 Top 10% +61% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: DRYWALL $25.39 $17.76 $43.15 Top 10% +79% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: FLOOR WORK $34.90 $17.21 $52.11 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: HIGH WORK OVER 60 FEET (CLARK, FRANKLIN, JEFFERSON, LEWIS, LINCOLN, MARION, PIKE, RALLS, ST. CHARLES, ST. LOUIS, AND WARREN COUNTIES) $29.11 $10.24 $39.35 Top 10% +63% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: LEAD ABATEMENT (CLARK, FRANKLIN, JEFFERSON, LEWIS, LINCOLN, MARION, PIKE, RALLS, ST. CHARLES, ST. LOUIS, AND WARREN COUNTIES) $29.36 $10.24 $39.60 Top 10% +64% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: PAPER HANGER $24.83 $17.76 $42.59 Top 10% +77% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: PAPER HANGER.$ 31.04 17.76 PAINTERS: DRYWALL $31.74 $17.76 $49.50 Top 10% +105% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: PRESSURE ROLLER; HIGH WORK UNDER 60 FT (CLARK, FRANKLIN, JEFFERSON, LEWIS, LINCOLN, MARION, PIKE, RALLS, ST. CHARLES, ST. LOUIS, AND WARREN $28.86 $10.24 $39.10 Top 10% +62% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: SANDBLASTER $40.76 $19.97 $60.73 Top 10% +152% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: SPRAY & ABRASIVE BLASTING; WATERBLASTING. HEIGHT RATES: 0VER 60 FT. $0.50 PER HOUR UNDER 60 FT. $0.25 PER HOUR $38.53 $17.92 $56.45 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: SPRAY.$ 34.90 17.21 PAINTERS: LEAD ABATEMENT $33.25 $17.21 $50.46 Top 10% +109% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: STEEPLEJACK $29.58 $17.76 $47.34 Bottom 10% +96% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: STEEPLEJACK $44.33 $19.97 $64.30 Top 10% +167% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: STEEPLEJACK.$ 36.98 17.76 PAINTERS: STAGEMAN; BELTMAN; STEELMAN; ELEVATOR SHAFT; BAZOOKA, BOXES AND POWER SANDER; SPRAYMAN; DIPPING $32.41 $17.76 $50.17 Top 10% +108% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: STRUCTURAL STEEL, SANDBLASTING AND ALL TANK WORK $35.90 $17.21 $53.11 Top 10% +120% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: TAPER (CLARK, FRANKLIN, JEFFERSON, LEWIS, LINCOLN, MARION, PIKE, RALLS, ST. CHARLES, ST. LOUIS, AND WARREN COUNTIES) $30.21 $10.24 $40.45 Top 10% +68% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: TAPING, PAPERHANGING $34.90 $17.21 $52.11 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: BRIDGES, DAMS, LOCKS OR POWERHOUSES $28.49 $15.03 $43.52 Top 10% +81% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: BRIDGES, STACKS & TANKS. HEIGHT RATES: OVER 60 FT. $0.50 PER HOUR. UNDER 60 FT. $0.25 PER HOUR $36.53 $17.92 $54.45 Top 10% +126% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: BRUSH & ROLLER. HEIGHT RATES: 0VER 60 FT. $0.50 PER HOUR UNDER 60 FT. $0.25 PER HOUR $29.80 $17.92 $47.72 Top 10% +98% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: BRUSH AND ROLL; TAPING, PAPERHANGING $26.49 $15.03 $41.52 Top 10% +72% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: EPOXY OR ANY TWO PART COATING; SANDBLASTING; STAGE OR OTHER AERIAL WORK - PLATFORMS OVER 50 FEET HIGH; LEAD ABATEMENT $27.49 $15.03 $42.52 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: FINISHER $20.18 $11.33 $31.51 Top 10% +31% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: PAINTER $19.75 $11.76 $31.51 Top 10% +31% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: SANDBLASTER, HIGH MAN, SPRAY MAN, VINYL HANGER, TOOL OPERATOR $21.18 $11.33 $32.51 Top 10% +35% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: SPRAY & ABRASIVE BLASTING; WATER BLASTING (CLARK, FRANKLIN, JEFFERSON, LEWIS, LINCOLN, MARION, PIKE, RALLS, ST. CHARLES, ST. LOUIS, AND WAR $30.61 $10.24 $40.85 Top 10% +69% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: SPRAY & ABRASIVE BLASTING; WATERBLASTING. HEIGHT RATES: OVER 60 FT. $0.50 PER HOUR. UNDER 60 FT. $0.25 PER HOUR $38.53 $17.92 $56.45 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: SPRAY; STRUCTURAL STEEL $27.49 $15.03 $42.52 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: STAGEMAN; BELTMAN; STEELMAN; ELEVATOR SHAFT; BAZOOKA, BOXES AND POWER SANDER; SPRAYMAN; DIPPING.$ 26.35 17.76 PAINTERS:: BRIDGEMAN; LEAD AB $26.73 $17.76 $44.49 Top 10% +85% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS:: TAPERS USING AMES OR COMPARABLE TOOLS $27.24 $15.03 $42.27 Top 10% +75% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTERS $55.56 $25.80 $81.36 Top 10% +173% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS $56.63 $24.54 $81.17 Top 10% +172% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS AND PIPEFITTERS $39.35 $15.72 $55.07 +84% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS AND PIPEFITTERS: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER (ADAIR, AUDRAIN, BOLLINGER $46.66 $21.99 $68.65 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS AND PIPEFITTERS: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION (ADAIR, AUDRAIN, BOLLINGER, BOONE $46.66 $21.99 $68.65 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS AND PIPEFITTERS: PROJECTS $750,000 & UNDER $32.78 $15.32 $48.10 Top 10% +61% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS AND PIPEFITTERS: PROJECTS OVER $750,000 $35.75 $15.32 $51.07 Top 10% +71% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER (CAMDEN, COLE, CRAWFORD, FRANKLIN, JEFFERSON, MA $46.66 $21.99 $68.65 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION (CAMDEN, COLE, CRAWFORD, FRANKLIN, JEFFERSON, MARIE $46.66 $21.99 $68.65 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 $40.17 $22.29 $62.46 Above median +116% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 $36.60 $19.32 $55.92 Bottom 10% +94% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 $45.96 $30.96 $76.92 Top 10% +166% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 (ADAIR, AUDRAIN, BOLLINGER, BOONE, BUTLER, CALLAWAY, CAPE GIRARDEAU, CARTER, CLARK, COLE, CRAWFORD, DENT, DUNKLIN $40.39 $30.33 $70.72 Top 10% +145% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 AREA 1 $38.83 $21.87 $60.70 Top 10% +110% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 $39.13 $22.29 $61.42 Above median +113% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 $36.25 $19.32 $55.57 Bottom 10% +92% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 $45.96 $30.96 $76.92 Top 10% +166% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 (ADAIR, AUDRAIN, BOLLINGER, BOONE, BUTLER, CALLAWAY, CAPE GIRARDEAU, CARTER, CLARK, COLE, CRAWFORD, DENT, DUNKLIN $40.04 $30.33 $70.37 Top 10% +144% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 AREA 1 $38.43 $21.87 $60.30 Top 10% +109% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 $34.66 $22.29 $56.95 Above median +97% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 $36.05 $19.32 $55.37 Bottom 10% +92% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 $44.66 $30.96 $75.62 Top 10% +162% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 (ADAIR, AUDRAIN, BOLLINGER, BOONE, BUTLER, CALLAWAY, CAPE GIRARDEAU, CARTER, CLARK, COLE, CRAWFORD, DENT, DUNKLIN $39.84 $30.33 $70.17 Top 10% +143% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 AREA 1 $36.43 $21.87 $58.30 Top 10% +102% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 $38.01 $22.29 $60.30 Above median +109% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 $34.00 $19.32 $53.32 Bottom 10% +85% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 $44.22 $30.96 $75.18 Top 10% +160% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 (ADAIR, AUDRAIN, BOLLINGER, BOONE, BUTLER, CALLAWAY, CAPE GIRARDEAU, CARTER, CLARK, COLE, CRAWFORD, DENT, DUNKLIN $36.19 $30.33 $66.52 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS, GROUP 1 FLAT BED TRUCKS SINGLE AXLE; STATION WAGONS; PICKUP TRUCKS; MATERIAL TRUCKS SINGLE AXLE; TANK WAGONS SINGLE AXLE $36.27 $15.85 $52.12 Top 10% +114% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS, GROUP 1 FLAT BED TRUCKS, SINGLE AXLE; STATION WAGONS; PICKUP TRUCKS; MATERIAL TRUCKS, SINGLE AXLE; TANK WAGON, SINGLE AXLE $36.57 $15.85 $52.42 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS, GROUP 2 AGITATOR AND TRANSIT MIX TRUCKS $36.72 $15.85 $52.57 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS, GROUP 2 AGITATOR AND TRANSIT MIX-TRUCKS $36.43 $15.85 $52.28 Top 10% +115% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS, GROUP 3 FLAT BED TRUCKS TANDEM AXLE; ARTICULATED DUMP TRUCKS; MATERIAL TRUCKS TANDEM AXLE; TANK WAGONS TANDEM AXLE $36.42 $15.85 $52.27 Top 10% +115% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS, GROUP 3 FLAT BED TRUCKS, TANDEM AXLE; ARTICULATED DUMP TRUCKS; MATERIAL TRUCKS, TANDEM AXLE; TANK WAGON, TANDEM AXLE $36.84 $15.85 $52.69 Top 10% +117% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS, GROUP 4 SEMI AND/OR POLE TRAILERS; WINCH, FORK & STEEL TRUCKS; DISTRIBUTOR DRIVERS & OPERATORS; TANK WAGONS SEMI- TRAILER; INSLEY WAGON $36.54 $15.85 $52.39 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS, GROUP 4 SEMI AND/OR POLE TRAILERS; WINCH, FORK & STEEL TRUCKS; DISTRIBUTOR DRIVERS AND OPERATORS; TANK WAGON, SEMI-TRAILER; INSLEY WAGO $36.73 $15.85 $52.58 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 $38.61 $15.85 $54.46 Top 10% +124% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 $37.83 $9.85 $47.68 Bottom 10% +96% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 FLAT BED TRUCKS SINGLE AXLE; STATION WAGONS; PICKUP TRUCKS; MATERIAL TRUCKS SINGLE AXLE; TANK WAGONS SINGLE AXLE $35.93 $15.75 $51.68 Top 10% +113% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 FLAT BED TRUCKS SINGLE AXLE; STATION WAGONS; PICKUP TRUCKS; MATERIAL TRUCKS SINGLE AXLE; TANK WAGONS SINGLE AXLE. ATCHISON, BAR $35.54 $15.85 $51.39 Top 10% +111% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 FLAT BED TRUCKS, SINGLE AXLE; STATION WAGONS; PICKUP TRUCKS; MATERIAL TRUCKS, SINGLE AXLE; TANK WAGON, SINGLE AXLE $37.58 $15.85 $53.43 Above median +120% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 FLAT BED TRUCKS, SINGLE AXLE; STATION WAGONS; PICKUP TRUCKS; MATERIAL TRUCKS, SINGLE AXLE; TANK WAGON, SINGLE AXLE $38.93 $15.85 $54.78 Top 10% +125% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 FLAT BED TRUCKS, SINGLE AXLE; STATION WAGONS; PICKUP TRUCKS; MATERIAL TRUCKS, SINGLE AXLE; TANK WAGON, SINGLE AXLE $35.84 $15.85 $51.69 Bottom 10% +113% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 $38.04 $15.85 $53.89 Top 10% +122% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 $37.83 $9.85 $47.68 Bottom 10% +96% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 AGITATOR AND TRANSIT MIX TRUCKS $38.73 $15.85 $54.58 Above median +125% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 AGITATOR AND TRANSIT MIX TRUCKS $39.08 $15.85 $54.93 Top 10% +126% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 AGITATOR AND TRANSIT MIX TRUCKS $35.99 $15.85 $51.84 Bottom 10% +113% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 AGITATOR AND TRANSIT MIX-TRUCKS $36.04 $15.75 $51.79 Top 10% +113% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 AGITATOR AND TRANSIT MIX-TRUCKS. ATCHISON, BARRY, GENTRY, GRUNDY, HARRISON, HOLT, MCDONALD, MERCER, NODAWAY, OZARK, STONE, SULL $35.70 $15.85 $51.55 Top 10% +112% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 3 $37.52 $15.85 $53.37 Top 10% +120% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 3 $37.83 $9.85 $47.68 Bottom 10% +96% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 3 FLAT BED TRUCKS TANDEM AXLE; ARTICULATED DUMP TRUCKS; MATERIAL TRUCKS TANDEM AXLE; TANK WAGONS TANDEM AXLE $36.08 $15.75 $51.83 Top 10% +113% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 3 FLAT BED TRUCKS TANDEM AXLE; ARTICULATED DUMP TRUCKS; MATERIAL TRUCKS TANDEM AXLE; TANK WAGONS TANDEM AXLE. ATCHISON, BARRY, GE $35.69 $15.85 $51.54 Top 10% +112% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 3 FLAT BED TRUCKS, TANDEM AXLE; ARTICULATED DUMP TRUCKS; MATERIAL TRUCKS, TANDEM AXLE; TANK WAGON, TANDEM AXLE $37.80 $15.85 $53.65 Above median +121% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 3 FLAT BED TRUCKS, TANDEM AXLE; ARTICULATED DUMP TRUCKS; MATERIAL TRUCKS, TANDEM AXLE; TANK WAGON, TANDEM AXLE $39.15 $15.85 $55.00 Top 10% +126% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 3 FLAT BED TRUCKS, TANDEM AXLE; ARTICULATED DUMP TRUCKS; MATERIAL TRUCKS, TANDEM AXLE; TANK WAGON, TANDEM AXLE $36.11 $15.85 $51.96 Bottom 10% +114% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 4 SEMI AND/OR POLE TRAILERS; WINCH, FORK & STEEL TRUCKS; DISTRIBUTOR DRIVERS & OPERATORS; TANK WAGONS SEMI- TRAILER; INSLEY WAGON $36.08 $15.75 $51.83 Top 10% +113% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 4 SEMI AND/OR POLE TRAILERS; WINCH, FORK & STEEL TRUCKS; DISTRIBUTOR DRIVERS & OPERATORS; TANK WAGONS SEMI- TRAILER; INSLEY WAGON $35.81 $15.85 $51.66 Bottom 10% +113% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 4 SEMI AND/OR POLE TRAILERS; WINCH, FORK & STEEL TRUCKS; DISTRIBUTOR DRIVERS AND OPERATORS; TANK WAGON, SEMI-TRAILER; INSLEY WAGO $39.04 $15.85 $54.89 Top 10% +126% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 4 SEMI AND/OR POLE TRAILERS; WINCH, FORK & STEEL TRUCKS; DISTRIBUTOR DRIVERS AND OPERATORS; TANK WAGON, SEMI-TRAILER; INSLEY WAGO $35.74 $15.85 $51.59 Bottom 10% +112% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 4 SEMI AND/OR POLE TRAILERS; WINCH, FORK & STEEL TRUCKS; DISTRIBUTOR DRIVERS AND OPERATORS; TANK WAGON, SEMI-TRAILER; INSLEY WAGO $37.69 $15.85 $53.54 Above median +120% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: TRAFFIC CONTROL SERVICE DRIVER. PAID HOLIDAYS: NEW YEAR'S DAY, DECORATION DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, EM $20.45 $0.00 $20.45 Top 10% -16% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Johnson, MO — Heavy construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Johnson

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MO20260001-15722-hvy →