Building Construction — Camden, Missouri

WD MO20260005-15871-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS WORKER/HEAT & FROST INSULATOR in Camden, Missouri (construction type: building) is $31.97/hr base + $14.00/hr fringe = $45.97/hr total package (WD MO20260005-15871-bld, Rev. 1).

Scroll down for all 31 trade classifications covered by this determination.

WD Number: MO20260005-15871-bld
Revision: 1
Construction Type: building
State: Missouri (MO)
County: Camden
Effective: May 17, 2026
Trades covered: 31
Official source: SAM.gov reference MO20260005View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKER/HEAT & FROST INSULATOR $31.97 $14.00 $45.97 +92% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER $27.66 $5.88 $33.54 -1% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $31.51 $22.25 $53.76 +83% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $31.39 $22.25 $53.64 +82% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $33.52 $15.88 $49.40 Above median +80% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $25.82 $8.24 $34.06 +0% vs market $0.00 $0.00 $0.00 $0.00
GLAZIER $29.87 $1.47 $31.34 +34% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, REINFORCING $21.02 $9.49 $30.51 Above median +5% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, STRUCTURAL $41.67 $31.25 $72.92 Top 10% +152% vs market $0.00 $0.00 $0.00 $0.00
LABORER $26.35 $13.01 $39.36 +52% vs market $0.00 $0.00 $0.00 $0.00
LABORER $29.08 $13.01 $42.09 Above median +63% vs market $0.00 $0.00 $0.00 $0.00
LABORER: ASBESTOS ABATEMENT $24.90 $0.00 $24.90 -4% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH ONLY $18.79 $8.12 $26.91 Top 10% +12% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: DRYWALL FINISHING/TAPING $33.90 $17.21 $51.11 Above median +112% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: ROLLER $18.79 $8.12 $26.91 Top 10% +12% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: SPRAY $18.79 $8.12 $26.91 +12% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION $50.66 $23.34 $74.00 Above median +148% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION $52.60 $29.93 $82.53 Above median +176% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION $50.66 $23.34 $74.00 Above median +148% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION $52.60 $29.93 $82.53 Above median +176% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR $27.91 $18.07 $45.98 Above median +59% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR $31.62 $18.07 $49.69 Above median +72% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $33.41 $18.07 $51.48 Above median +78% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: BULLDOZER $31.62 $18.07 $49.69 Above median +72% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GRADER/BLADE $31.62 $18.07 $49.69 Above median +72% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: ROLLER $30.91 $18.07 $48.98 Above median +70% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $33.60 $19.99 $53.59 Above median +109% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION $47.20 $26.28 $73.48 Above median +130% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $45.94 $27.53 $73.47 Above median +146% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $32.79 $21.31 $54.10 Above median +86% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $25.57 $0.00 $25.57 Above median +5% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Camden, MO — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Camden

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MO20260005-15871-bld →