Building Construction — Wilkin, Minnesota

WD MN20260110-15541-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ARTICULATED HAULER in Wilkin, Minnesota (construction type: building) is $18.75/hr base + $0.00/hr fringe = $18.75/hr total package (WD MN20260110-15541-bld, Rev. 1).

Scroll down for all 56 trade classifications covered by this determination.

WD Number: MN20260110-15541-bld
Revision: 1
Construction Type: building
State: Minnesota (MN)
County: Wilkin
Effective: May 17, 2026
Trades covered: 56
Official source: SAM.gov reference MN20260110View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ARTICULATED HAULER $18.75 $0.00 $18.75 Bottom 10% $0.00 $0.00 $0.00 $0.00
ASBESTOS ABATEMENT WORKER $36.23 $22.26 $58.49 $0.00 $0.00 $0.00 $0.00
BLASTER $17.50 $1.85 $19.35 Bottom 10% $0.00 $0.00 $0.00 $0.00
BOILERMAKER $46.00 $31.93 $77.93 +58% vs market $0.00 $0.00 $0.00 $0.00
BOOM TRUCK $20.00 $0.91 $20.91 Bottom 10% $0.00 $0.00 $0.00 $0.00
BRICKLAYER $41.73 $29.01 $70.74 Above median +65% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $31.00 $6.64 $37.64 +21% vs market $0.00 $0.00 $0.00 $0.00
CARPET LAYER $23.47 $15.67 $39.14 -1% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON $40.32 $20.69 $61.01 Above median +100% vs market $0.00 $0.00 $0.00 $0.00
DRUMS); MECHANIC; POWER PLANT; PUMP OPERATOR AND/OR CONVEYOR; SELF-ERECTING TOWER CRANE UNDER 100 FEET MEASURED FROM BOOM FOOT PIN; STRADDLE CARRIER $33.75 $14.49 $48.24 Bottom 10% $0.00 $0.00 $0.00 $0.00
DRYWALL TAPER $33.76 $23.84 $57.60 +92% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $34.00 $9.55 $43.55 +11% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR CONSTRUCTORS $62.52 $45.36 $107.88 Top 10% +91% vs market $0.00 $0.00 $0.00 $0.00
FLAG PERSON $29.53 $20.62 $50.15 Above median $0.00 $0.00 $0.00 $0.00
GLAZIER $36.49 $21.85 $58.34 Above median +81% vs market $0.00 $0.00 $0.00 $0.00
HEATING AND FROST INSULATORS $29.14 $19.11 $48.25 $0.00 $0.00 $0.00 $0.00
IRONWORKER $41.19 $35.68 $76.87 Above median +71% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $21.77 $5.73 $27.50 Above median -3% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $17.00 $2.00 $19.00 Above median -33% vs market $0.00 $0.00 $0.00 $0.00
LABORER: SKILLED $36.06 $24.39 $60.45 +114% vs market $0.00 $0.00 $0.00 $0.00
LANDSCAPING EQUIPMENT (INCLUDES HYDRO SEEDER OR MULCHER, SOD ROLLER, FARM TRACTOR WITH ATTACHMENT SPECIFICLLY SEEDING, SODDING, OR PLANT, AND TWO-FRAM $15.00 $0.00 $15.00 Bottom 10% $0.00 $0.00 $0.00 $0.00
LATHER $27.03 $23.70 $50.73 Above median $0.00 $0.00 $0.00 $0.00
METERS/164 FEET OF BOOM AND OVER; PILE DRIVING WHEN THREE DRUMS IN USE; TRUCK OR CRAWLER CRANE WITH 150 FEET OF BOOM UP TO AND NOT INCLUDING 200 FEET $43.03 $22.85 $65.88 Bottom 10% $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $37.15 $19.90 $57.05 +71% vs market $0.00 $0.00 $0.00 $0.00
PAINTER $34.23 $25.28 $59.51 Top 10% +103% vs market $0.00 $0.00 $0.00 $0.00
PAVEMENT MARKING OR MARKING REMOVAL EQUIPMENT (; SELF-PROPELLED TRUCK OR TRAILER MOUNTED UNITS.) $24.86 $10.59 $35.45 Above median $0.00 $0.00 $0.00 $0.00
PILEDRIVER $49.46 $30.23 $79.69 Above median $0.00 $0.00 $0.00 $0.00
PIPEFITTER/STEAMFITTER $43.54 $20.89 $64.43 +61% vs market $0.00 $0.00 $0.00 $0.00
PIPELAYER $26.54 $18.05 $44.59 $0.00 $0.00 $0.00 $0.00
PLASTERER $30.72 $18.33 $49.05 +50% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $43.54 $20.89 $64.43 Above median +61% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 3: ALL-TERRAIN VEHICLE CRANES; CONCRETE PUMP 32-49 METERS/102-164 FEET; DERRICK; SELF-ERECTING TOWER CRANE $34.00 $8.60 $42.60 Bottom 10% +13% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 4: CRAWLER BACKHOE INCLUDING ATTACHMENTS; FIREPERSON, CHIEF BOILER LICENSE; HOIST ENGINEER; LOCOMOTIVE; OVE $31.50 $0.00 $31.50 Bottom 10% -17% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 6: CONCRETE BATCH PLANT; FIREPERSON, FIRST CLASS BOILER LICENSE; FRONT END, SKID STEER UP TO 1 C YD; GUNITE $21.00 $6.55 $27.55 Bottom 10% -27% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 8: ELEVATOR OPERATOR; GREASER; MECHANICAL SPACE HEATER $30.90 $19.45 $50.35 +33% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 2: GRADER OR MOTOR PATROL; TUGBOAT 100 H.P. AND OVER WHEN LICENSE REQUIRED $28.00 $0.00 $28.00 -26% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 4: AIR TRACK ROCK DRILL; AUTOMATIC ROAD MACHINE; BACKFILLER OPERATOR; BITUMINOUS ROLLERS, RUBBER TIRED O $33.92 $26.40 $60.32 Above median +60% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 5: BITUMINOUS ROLLER; CONCRETE SAW; FORM TRENCH DIGGER; HYDRAULIC LOG SPLITTER; LOADER; POST HOLE DRIVIN $19.15 $11.70 $30.85 -18% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 6: CAT, CHALLENGER, OR SIMILAR TYPE OF TRACTORS, WHEN PULLING DISK OR ROLLER; DREDGE DECK HAND; GRAVEL S $14.00 $0.00 $14.00 Bottom 10% -63% vs market $0.00 $0.00 $0.00 $0.00
PUMP/PUMPCRETE OR COMPLACO TYPE; FIREPERSON, TEMPORARY HEAT SECOND CLASS BOILER LICENSE; OILER; PICK UP SWEEPER; PUMP AND/OR CONVEYOR $37.49 $22.85 $60.34 Bottom 10% $0.00 $0.00 $0.00 $0.00
ROOFER $39.01 $21.93 $60.94 Above median +63% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $37.01 $23.51 $60.52 Above median +101% vs market $0.00 $0.00 $0.00 $0.00
SIGN ERECTOR $31.07 $18.75 $49.82 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $43.53 $26.67 $70.20 +75% vs market $0.00 $0.00 $0.00 $0.00
SURVEY FIELD TECHNICIAN $14.00 $0.00 $14.00 Bottom 10% $0.00 $0.00 $0.00 $0.00
TERRAZZO WORKER $37.58 $16.83 $54.41 Bottom 10% $0.00 $0.00 $0.00 $0.00
TILE FINISHER $22.80 $5.39 $28.19 -5% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $17.44 $5.81 $23.25 -22% vs market $0.00 $0.00 $0.00 $0.00
TRAFFIC CONTROL PERSON $14.00 $0.00 $14.00 Bottom 10% $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 1: MECHANIC; TRACTOR TRAILER DRIVER; TRUCK DRIVER $17.00 $0.00 $17.00 Bottom 10% -42% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 2: FOUR OR MORE AXLE UNIT, STRAIGHT BODY TRUCK $21.00 $0.00 $21.00 Bottom 10% -28% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 3: BITUMINOUS DISTRIBUTOR DRIVER; BITUMINOUS DISTRIBUTOR; THREE AXLE UNITS $16.00 $0.00 $16.00 Bottom 10% -46% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 4: BITUMINOUS DISTRIBUTOR SPRAY OPERATOR; DUMP PERSON; GREASER; PILOT CAR DRIVER; RUBBER-TIRED, SELF-PROPELLED PACKER UNDER 8 TONS $15.50 $0.47 $15.97 Bottom 10% -46% vs market $0.00 $0.00 $0.00 $0.00
UNDERGROUND AND OPEN DITCH LABORER $24.74 $18.05 $42.79 Bottom 10% $0.00 $0.00 $0.00 $0.00
WIRING SYSTEM TECHNICIAN $44.61 $20.98 $65.59 $0.00 $0.00 $0.00 $0.00
WIRING SYSTEMS INSTALLER $30.49 $15.03 $45.52 $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Wilkin, MN — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Wilkin

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MN20260110-15541-bld →