Building Construction — Traverse, Minnesota

WD MN20260104-15608-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ARTICULATED HAULER in Traverse, Minnesota (construction type: building) is $21.50/hr base + $0.00/hr fringe = $21.50/hr total package (WD MN20260104-15608-bld, Rev. 1).

Scroll down for all 48 trade classifications covered by this determination.

WD Number: MN20260104-15608-bld
Revision: 1
Construction Type: building
State: Minnesota (MN)
County: Traverse
Effective: May 17, 2026
Trades covered: 48
Official source: SAM.gov reference MN20260104View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ARTICULATED HAULER $21.50 $0.00 $21.50 Bottom 10% $0.00 $0.00 $0.00 $0.00
ASBESTOS ABATEMENT WORKER $41.23 $25.99 $67.22 Top 10% $0.00 $0.00 $0.00 $0.00
BOILERMAKER $41.94 $29.99 $71.93 +46% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER $41.73 $29.01 $70.74 Above median +65% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $33.14 $27.60 $60.74 Above median +95% vs market $0.00 $0.00 $0.00 $0.00
CARPET LAYER $33.92 $12.67 $46.59 +18% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON $29.75 $20.48 $50.23 +64% vs market $0.00 $0.00 $0.00 $0.00
DRUMS); MECHANIC; POWER PLANT; PUMP OPERATOR AND/OR CONVEYOR; SELF-ERECTING TOWER CRANE UNDER 100 FEET MEASURED FROM BOOM FOOT PIN; STRADDLE CARRIER $39.17 $21.70 $60.87 Bottom 10% $0.00 $0.00 $0.00 $0.00
DRYWALL TAPER $33.76 $23.84 $57.60 +92% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $38.05 $17.96 $56.01 +43% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR CONSTRUCTORS $51.55 $40.48 $92.03 Bottom 10% +63% vs market $0.00 $0.00 $0.00 $0.00
GLAZIER $36.49 $21.85 $58.34 Above median +81% vs market $0.00 $0.00 $0.00 $0.00
HEATING AND FROST INSULATORS $57.24 $31.95 $89.19 Top 10% $0.00 $0.00 $0.00 $0.00
IRONWORKER $29.00 $3.77 $32.77 Bottom 10% -27% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $21.77 $5.73 $27.50 Above median -3% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $17.50 $0.00 $17.50 Above median -38% vs market $0.00 $0.00 $0.00 $0.00
LABORER: SKILLED $36.06 $24.39 $60.45 +114% vs market $0.00 $0.00 $0.00 $0.00
LANDSCAPING EQUIPMENT (INCLUDES HYDRO SEEDER OR MULCHER, SOD ROLLER, FARM TRACTOR WITH ATTACHMENT SPECIFICLLY SEEDING, SODDING, OR PLANT, AND TWO-FRAM $11.13 $0.00 $11.13 Bottom 10% $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $11.13 $0.00 $11.13 Bottom 10% -67% vs market $0.00 $0.00 $0.00 $0.00
PAINTER $34.23 $25.28 $59.51 Top 10% +103% vs market $0.00 $0.00 $0.00 $0.00
PAVEMENT MARKING OR MARKING REMOVAL EQUIPMENT (; SELF-PROPELLED TRUCK OR TRAILER MOUNTED UNITS.) $14.24 $0.76 $15.00 Bottom 10% $0.00 $0.00 $0.00 $0.00
PILEDRIVER $27.46 $16.11 $43.57 Bottom 10% $0.00 $0.00 $0.00 $0.00
PIPEFITTER/STEAMFITTER $43.54 $20.89 $64.43 +61% vs market $0.00 $0.00 $0.00 $0.00
PIPELAYER $23.89 $14.90 $38.79 $0.00 $0.00 $0.00 $0.00
PLASTERER $25.47 $14.88 $40.35 +23% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $43.54 $20.89 $64.43 Above median +61% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 1: HELICOPTER PILOT; TOWER CRANE 250 FEET AND OVER; TRUCK CRAWLER CRANE WITH 200 FEET OF BOOM AND OVER, INC $38.15 $19.45 $57.60 Bottom 10% +52% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 3: ALL-TERRAIN VEHICLE CRANES; CONCRETE PUMP 32-49 METERS/102-164 FEET; DERRICK; SELF-ERECTING TOWER CRANE $27.50 $9.07 $36.57 Bottom 10% -3% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 4: CRAWLER BACKHOE INCLUDING ATTACHMENTS; FIREPERSON, CHIEF BOILER LICENSE; HOIST ENGINEER; LOCOMOTIVE; OVE $31.50 $0.00 $31.50 Bottom 10% -17% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 6: CONCRETE BATCH PLANT; FIREPERSON, FIRST CLASS BOILER LICENSE; FRONT END, SKID STEER UP TO 1 C YD; GUNITE $21.00 $6.55 $27.55 Bottom 10% -27% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 2: GRADER OR MOTOR PATROL; TUGBOAT 100 H.P. AND OVER WHEN LICENSE REQUIRED $31.50 $0.00 $31.50 -17% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 4: AIR TRACK ROCK DRILL; AUTOMATIC ROAD MACHINE; BACKFILLER OPERATOR; BITUMINOUS ROLLERS, RUBBER TIRED O $36.50 $0.00 $36.50 -3% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 5: BITUMINOUS ROLLER; CONCRETE SAW; FORM TRENCH DIGGER; HYDRAULIC LOG SPLITTER; LOADER; POST HOLE DRIVIN $26.00 $0.00 $26.00 Bottom 10% -31% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 6: CAT, CHALLENGER, OR SIMILAR TYPE OF TRACTORS, WHEN PULLING DISK OR ROLLER; DREDGE DECK HAND; GRAVEL S $14.00 $0.00 $14.00 Bottom 10% -63% vs market $0.00 $0.00 $0.00 $0.00
PUMP/PUMPCRETE OR COMPLACO TYPE; FIREPERSON, TEMPORARY HEAT SECOND CLASS BOILER LICENSE; OILER; PICK UP SWEEPER; PUMP AND/OR CONVEYOR $17.75 $0.00 $17.75 Bottom 10% $0.00 $0.00 $0.00 $0.00
ROOFER $41.81 $21.93 $63.74 Above median +71% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $48.15 $29.12 $77.27 Above median +157% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $43.53 $26.67 $70.20 +75% vs market $0.00 $0.00 $0.00 $0.00
TERRAZZO WORKER $37.58 $16.83 $54.41 Bottom 10% $0.00 $0.00 $0.00 $0.00
TILE FINISHER $22.80 $5.39 $28.19 -5% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $30.66 $10.53 $41.19 +39% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 1: MECHANIC; TRACTOR TRAILER DRIVER; TRUCK DRIVER $18.00 $1.25 $19.25 Bottom 10% -34% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 2: FOUR OR MORE AXLE UNIT, STRAIGHT BODY TRUCK $26.00 $0.00 $26.00 Bottom 10% -11% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 3: BITUMINOUS DISTRIBUTOR DRIVER; BITUMINOUS DISTRIBUTOR; THREE AXLE UNITS $23.66 $16.20 $39.86 +36% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 4: BITUMINOUS DISTRIBUTOR SPRAY OPERATOR; DUMP PERSON; GREASER; PILOT CAR DRIVER; RUBBER-TIRED, SELF-PROPELLED PACKER UNDER 8 TONS $16.00 $0.00 $16.00 Bottom 10% -46% vs market $0.00 $0.00 $0.00 $0.00
UNDERGROUND AND OPEN DITCH LABORER $22.09 $14.90 $36.99 Bottom 10% $0.00 $0.00 $0.00 $0.00
WIRING SYSTEM TECHNICIAN $41.42 $18.16 $59.58 $0.00 $0.00 $0.00 $0.00
WIRING SYSTEMS INSTALLER $28.14 $14.71 $42.85 $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Traverse, MN — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Traverse

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MN20260104-15608-bld →