Building Construction — Pope, Minnesota
WD MN20260087-15596-bld · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for ARTICULATED HAULER in Pope, Minnesota (construction type: building) is $44.54/hr base + $26.88/hr fringe = $71.42/hr total package (WD MN20260087-15596-bld, Rev. 1).
Scroll down for all 56 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| ARTICULATED HAULER | $44.54 | $26.88 | $71.42 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| ASBESTOS ABATEMENT WORKER | $41.23 | $25.99 | $67.22 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| BOILERMAKER | $46.00 | $31.93 | $77.93 +58% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| BOOM TRUCK | $44.54 | $26.88 | $71.42 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $41.73 | $29.01 | $70.74 Above median +65% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $33.14 | $27.60 | $60.74 Above median +95% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPET LAYER | $34.23 | $25.38 | $59.61 Above median +51% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON | $50.06 | $25.45 | $75.51 Top 10% +147% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| DRUMS); MECHANIC; POWER PLANT; PUMP OPERATOR AND/OR CONVEYOR; SELF-ERECTING TOWER CRANE UNDER 100 FEET MEASURED FROM BOOM FOOT PIN; STRADDLE CARRIER | $44.54 | $26.88 | $71.42 | $0.00 | $0.00 | $0.00 | $0.00 |
| DRYWALL TAPER | $35.31 | $24.43 | $59.74 Above median +99% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $46.00 | $30.00 | $76.00 Above median +94% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELEVATOR CONSTRUCTORS | $62.52 | $45.36 | $107.88 Top 10% +91% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| FLAG PERSON | $37.66 | $23.97 | $61.63 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| GLAZIER | $36.49 | $21.85 | $58.34 Above median +81% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| HEATING AND FROST INSULATORS | $57.24 | $31.95 | $89.19 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER | $44.85 | $35.72 | $80.57 Above median +80% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $37.66 | $24.41 | $62.07 Top 10% +120% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: LANDSCAPE | $26.89 | $19.31 | $46.20 Above median +64% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: SKILLED | $37.66 | $24.41 | $62.07 Above median +120% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LANDSCAPING EQUIPMENT (INCLUDES HYDRO SEEDER OR MULCHER, SOD ROLLER, FARM TRACTOR WITH ATTACHMENT SPECIFICLLY SEEDING, SODDING, OR PLANT, AND TWO-FRAM | $26.89 | $19.31 | $46.20 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| LATHER | $33.14 | $26.85 | $59.99 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| METERS/164 FEET OF BOOM AND OVER; PILE DRIVING WHEN THREE DRUMS IN USE; TRUCK OR CRAWLER CRANE WITH 150 FEET OF BOOM UP TO AND NOT INCLUDING 200 FEET | $48.53 | $26.88 | $75.41 | $0.00 | $0.00 | $0.00 | $0.00 |
| MILLWRIGHT | $41.66 | $35.40 | $77.06 Above median +131% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER | $34.23 | $25.28 | $59.51 Top 10% +103% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PILEDRIVER | $41.14 | $27.05 | $68.19 | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER/STEAMFITTER | $48.24 | $34.70 | $82.94 Above median +107% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPELAYER | $38.00 | $24.26 | $62.26 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| PLASTERER | $45.98 | $24.45 | $70.43 Top 10% +115% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $54.79 | $30.58 | $85.37 Above median +113% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 1: HELICOPTER PILOT; TOWER CRANE 250 FEET AND OVER; TRUCK CRAWLER CRANE WITH 200 FEET OF BOOM AND OVER, INC | $47.19 | $25.20 | $72.39 +92% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 3: ALL-TERRAIN VEHICLE CRANES; CONCRETE PUMP 32-49 METERS/102-164 FEET; DERRICK; SELF-ERECTING TOWER CRANE | $47.02 | $26.88 | $73.90 +96% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 4: CRAWLER BACKHOE INCLUDING ATTACHMENTS; FIREPERSON, CHIEF BOILER LICENSE; HOIST ENGINEER; LOCOMOTIVE; OVE | $46.67 | $26.40 | $73.07 +93% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 6: CONCRETE BATCH PLANT; FIREPERSON, FIRST CLASS BOILER LICENSE; FRONT END, SKID STEER UP TO 1 C YD; GUNITE | $42.94 | $26.88 | $69.82 Above median +85% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 8: ELEVATOR OPERATOR; GREASER; MECHANICAL SPACE HEATER | $16.10 | $6.00 | $22.10 -42% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 2: GRADER OR MOTOR PATROL; TUGBOAT 100 H.P. AND OVER WHEN LICENSE REQUIRED | $34.94 | $26.79 | $61.73 Above median +63% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 3: ASPHALT BITUMINOUS STABILIZER PLANT; CABLEWAY; DERRICK; DREDGE OR ENGINEERS, DREDGE AND ENGINEER; LOC | $32.26 | $25.00 | $57.26 Above median +52% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 4: AIR TRACK ROCK DRILL; AUTOMATIC ROAD MACHINE; BACKFILLER OPERATOR; BITUMINOUS ROLLERS, RUBBER TIRED O | $33.58 | $26.79 | $60.37 Above median +60% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 5: BITUMINOUS ROLLER; CONCRETE SAW; FORM TRENCH DIGGER; HYDRAULIC LOG SPLITTER; LOADER; POST HOLE DRIVIN | $31.71 | $26.79 | $58.50 Above median +55% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 6: CAT, CHALLENGER, OR SIMILAR TYPE OF TRACTORS, WHEN PULLING DISK OR ROLLER; DREDGE DECK HAND; GRAVEL S | $31.06 | $26.40 | $57.46 Above median +52% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PUMP/PUMPCRETE OR COMPLACO TYPE; FIREPERSON, TEMPORARY HEAT SECOND CLASS BOILER LICENSE; OILER; PICK UP SWEEPER; PUMP AND/OR CONVEYOR | $41.73 | $26.88 | $68.61 | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $41.06 | $22.68 | $63.74 Above median +71% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER | $48.15 | $29.12 | $77.27 Above median +157% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SIGN ERECTOR | $37.19 | $19.88 | $57.07 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $43.53 | $26.67 | $70.20 +75% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SURVEY FIELD TECHNICIAN, +$950,000 | $28.11 | $17.69 | $45.80 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| SURVEY FIELD TECHNICIAN, -$950,000 | $26.36 | $17.69 | $44.05 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| TERRAZZO WORKER | $38.91 | $19.40 | $58.31 | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE FINISHER | $14.00 | $0.00 | $14.00 Bottom 10% -53% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE SETTER | $25.00 | $0.00 | $25.00 -16% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 1: MECHANIC; TRACTOR TRAILER DRIVER; TRUCK DRIVER | $28.00 | $0.84 | $28.84 Bottom 10% -2% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 2: FOUR OR MORE AXLE UNIT, STRAIGHT BODY TRUCK | $23.10 | $6.91 | $30.01 +2% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 3: BITUMINOUS DISTRIBUTOR DRIVER; BITUMINOUS DISTRIBUTOR; THREE AXLE UNITS | $25.00 | $6.91 | $31.91 +9% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 4: BITUMINOUS DISTRIBUTOR SPRAY OPERATOR; DUMP PERSON; GREASER; PILOT CAR DRIVER; RUBBER-TIRED, SELF-PROPELLED PACKER UNDER 8 TONS | $23.00 | $6.76 | $29.76 +1% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| UNDERGROUND AND OPEN DITCH LABORER | $36.00 | $24.26 | $60.26 | $0.00 | $0.00 | $0.00 | $0.00 |
| WIRING SYSTEM TECHNICIAN | $47.73 | $22.24 | $69.97 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| WIRING SYSTEMS INSTALLER | $33.44 | $17.82 | $51.26 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Pope, MN — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Pope
Compliance Notes
- This wage determination applies to federal contracts for building construction in Pope, Minnesota.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.