Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS ABATEMENT WORKER in Otter Tail, Minnesota (construction type: building) is $41.23/hr base + $25.99/hr fringe = $67.22/hr total package (WD MN20260082-15533-bld, Rev. 1).

Scroll down for all 56 trade classifications covered by this determination.

WD Number: MN20260082-15533-bld
Revision: 1
Construction Type: building
State: Minnesota (MN)
County: Otter Tail
Effective: May 17, 2026
Trades covered: 56
Official source: SAM.gov reference MN20260082View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS ABATEMENT WORKER $41.23 $25.99 $67.22 Top 10% $0.00 $0.00 $0.00 $0.00
BLASTER $21.33 $9.01 $30.34 Above median $0.00 $0.00 $0.00 $0.00
BOILERMAKER $46.00 $31.93 $77.93 +58% vs market $0.00 $0.00 $0.00 $0.00
BOOM TRUCK $20.00 $0.91 $20.91 Bottom 10% $0.00 $0.00 $0.00 $0.00
BRICKLAYER $41.73 $29.01 $70.74 Above median +65% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $23.50 $5.54 $29.04 -7% vs market $0.00 $0.00 $0.00 $0.00
CARPET LAYER $23.47 $15.67 $39.14 -1% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON $42.40 $22.57 $64.97 Above median +112% vs market $0.00 $0.00 $0.00 $0.00
DRUMS); MECHANIC; POWER PLANT; PUMP OPERATOR AND/OR CONVEYOR; SELF-ERECTING TOWER CRANE UNDER 100 FEET MEASURED FROM BOOM FOOT PIN; STRADDLE CARRIER $44.91 $25.20 $70.11 $0.00 $0.00 $0.00 $0.00
DRYWALL TAPER $33.76 $23.84 $57.60 +92% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $38.05 $17.96 $56.01 +43% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR CONSTRUCTORS $62.52 $45.36 $107.88 Top 10% +91% vs market $0.00 $0.00 $0.00 $0.00
FLAG PERSON $29.53 $20.62 $50.15 Above median $0.00 $0.00 $0.00 $0.00
GLAZIER $36.49 $21.85 $58.34 Above median +81% vs market $0.00 $0.00 $0.00 $0.00
HEATING AND FROST INSULATORS $29.14 $19.11 $48.25 $0.00 $0.00 $0.00 $0.00
IRONWORKER $44.85 $35.72 $80.57 Above median +80% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $36.06 $24.39 $60.45 Top 10% +114% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $20.00 $2.00 $22.00 Above median -22% vs market $0.00 $0.00 $0.00 $0.00
LABORER: SKILLED $36.06 $24.39 $60.45 +114% vs market $0.00 $0.00 $0.00 $0.00
LANDSCAPING EQUIPMENT (INCLUDES HYDRO SEEDER OR MULCHER, SOD ROLLER, FARM TRACTOR WITH ATTACHMENT SPECIFICALLY SEEDING, SODDING, OR PLANT, AND TWO-FRA $24.00 $2.00 $26.00 Bottom 10% $0.00 $0.00 $0.00 $0.00
LATHER $27.03 $23.70 $50.73 Above median $0.00 $0.00 $0.00 $0.00
METERS/164 FEET OF BOOM AND OVER; PILE DRIVING WHEN THREE DRUMS IN USE; TRUCK OR CRAWLER CRANE WITH 150 FEET OF BOOM UP TO AND NOT INCLUDING 200 FEET $48.53 $26.88 $75.41 $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $38.25 $24.21 $62.46 +87% vs market $0.00 $0.00 $0.00 $0.00
PAINTER $33.00 $6.53 $39.53 Above median +35% vs market $0.00 $0.00 $0.00 $0.00
PAVEMENT MARKING OR MARKING REMOVAL EQUIPMENT (; SELF-PROPELLED TRUCK OR TRAILER MOUNTED UNITS.) $30.25 $17.65 $47.90 Above median $0.00 $0.00 $0.00 $0.00
PILEDRIVER $49.46 $30.23 $79.69 Above median $0.00 $0.00 $0.00 $0.00
PIPEFITTER/STEAMFITTER $43.54 $20.89 $64.43 +61% vs market $0.00 $0.00 $0.00 $0.00
PIPELAYER $38.00 $24.26 $62.26 Above median $0.00 $0.00 $0.00 $0.00
PLASTERER $33.22 $18.33 $51.55 Above median +57% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $43.54 $20.89 $64.43 Above median +61% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 1: HELICOPTER PILOT; TOWER CRANE 250 FEET AND OVER; TRUCK CRAWLER CRANE WITH 200 FEET OF BOOM AND OVER, INC $48.89 $26.88 $75.77 Above median +101% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 3: ALL-TERRAIN VEHICLE CRANES; CONCRETE PUMP 32-49 METERS/102-164 FEET; DERRICK; SELF-ERECTING TOWER CRANE $47.02 $26.88 $73.90 +96% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 4: CRAWLER BACKHOE INCLUDING ATTACHMENTS; FIREPERSON, CHIEF BOILER LICENSE; HOIST ENGINEER; LOCOMOTIVE; OVE $46.99 $25.20 $72.19 +91% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 6: CONCRETE BATCH PLANT; FIREPERSON, FIRST CLASS BOILER LICENSE; FRONT END, SKID STEER UP TO 1 C YD; GUNITE $37.75 $21.70 $59.45 +57% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 2: GRADER OR MOTOR PATROL; TUGBOAT 100 H.P. AND OVER WHEN LICENSE REQUIRED $24.00 $3.00 $27.00 Bottom 10% -29% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 3: ASPHALT BITUMINOUS STABILIZER PLANT; CABLEWAY; DERRICK; DREDGE OR ENGINEERS, DREDGE AND ENGINEER; LOC $31.00 $8.75 $39.75 +5% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 4: AIR TRACK ROCK DRILL; AUTOMATIC ROAD MACHINE; BACKFILLER OPERATOR; BITUMINOUS ROLLERS, RUBBER TIRED O $38.00 $0.00 $38.00 +1% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 5: BITUMINOUS ROLLER; CONCRETE SAW; FORM TRENCH DIGGER; HYDRAULIC LOG SPLITTER; LOADER; POST HOLE DRIVIN $33.00 $0.00 $33.00 -13% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 6: CAT, CHALLENGER, OR SIMILAR TYPE OF TRACTORS, WHEN PULLING DISK OR ROLLER; DREDGE DECK HAND; GRAVEL S $17.00 $3.00 $20.00 Bottom 10% -47% vs market $0.00 $0.00 $0.00 $0.00
PUMP/PUMPCRETE OR COMPLACO TYPE; FIREPERSON, TEMPORARY HEAT SECOND CLASS BOILER LICENSE; OILER; PICK UP SWEEPER; PUMP AND/OR CONVEYOR $41.73 $26.88 $68.61 $0.00 $0.00 $0.00 $0.00
ROOFER $39.01 $21.93 $60.94 Above median +63% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $48.15 $29.12 $77.27 Above median +157% vs market $0.00 $0.00 $0.00 $0.00
SIGN ERECTOR $37.19 $19.88 $57.07 Top 10% $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $43.53 $26.67 $70.20 +75% vs market $0.00 $0.00 $0.00 $0.00
SURVEY FIELD TECHNICIAN $23.56 $15.03 $38.59 $0.00 $0.00 $0.00 $0.00
TERRAZZO WORKER $43.73 $20.73 $64.46 Above median $0.00 $0.00 $0.00 $0.00
TILE FINISHER $25.21 $5.46 $30.67 +3% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $17.44 $5.81 $23.25 -22% vs market $0.00 $0.00 $0.00 $0.00
TRAFFIC CONTROL PERSON $15.00 $0.00 $15.00 Bottom 10% $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 1: MECHANIC; TRACTOR TRAILER DRIVER; TRUCK DRIVER $28.00 $0.84 $28.84 Bottom 10% -2% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 2: FOUR OR MORE AXLE UNIT, STRAIGHT BODY TRUCK $33.00 $8.75 $41.75 +42% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 3: BITUMINOUS DISTRIBUTOR DRIVER; BITUMINOUS DISTRIBUTOR; THREE AXLE UNITS $16.00 $0.00 $16.00 Bottom 10% -46% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 4: BITUMINOUS DISTRIBUTOR SPRAY OPERATOR; DUMP PERSON; GREASER; PILOT CAR DRIVER; RUBBER-TIRED, SELF-PROPELLED PACKER UNDER 8 TONS $11.50 $1.81 $13.31 Bottom 10% -55% vs market $0.00 $0.00 $0.00 $0.00
UNDERGROUND AND OPEN DITCH LABORER $36.00 $24.26 $60.26 $0.00 $0.00 $0.00 $0.00
WIRING SYSTEM TECHNICIAN $47.73 $22.24 $69.97 Top 10% $0.00 $0.00 $0.00 $0.00
WIRING SYSTEMS INSTALLER $33.44 $17.82 $51.26 Top 10% $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Otter Tail, MN — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Otter Tail

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MN20260082-15533-bld →