Building Construction — Crow Wing, Minnesota
WD MN20260044-15523-bld · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for ASBESTOS ABATEMENT WORKER in Crow Wing, Minnesota (construction type: building) is $36.23/hr base + $22.26/hr fringe = $58.49/hr total package (WD MN20260044-15523-bld, Rev. 1).
Scroll down for all 56 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| ASBESTOS ABATEMENT WORKER | $36.23 | $22.26 | $58.49 | $0.00 | $0.00 | $0.00 | $0.00 |
| BOILERMAKER | $41.39 | $28.82 | $70.21 +42% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| BOOM TRUCK | $18.82 | $4.57 | $23.39 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $43.41 | $28.50 | $71.91 Above median +68% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $32.00 | $24.95 | $56.95 +83% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPET LAYER | $32.00 | $24.95 | $56.95 Above median +44% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON | $39.40 | $22.16 | $61.56 Above median +101% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| DRUMS); MECHANIC; POWER PLANT; PUMP OPERATOR AND/OR CONVEYOR; SELF-ERECTING TOWER CRANE UNDER 100 FEET MEASURED FROM BOOM FOOT PIN; STRADDLE CARRIER | $44.91 | $25.20 | $70.11 | $0.00 | $0.00 | $0.00 | $0.00 |
| DRYWALL TAPER | $33.76 | $23.84 | $57.60 +92% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $48.01 | $32.79 | $80.80 Top 10% +106% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELEVATOR CONSTRUCTORS | $59.95 | $44.53 | $104.48 +85% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| FLAG PERSON | $13.03 | $5.37 | $18.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| GLAZIER | $36.49 | $21.85 | $58.34 Above median +81% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| HEATING AND FROST INSULATORS | $50.51 | $23.45 | $73.96 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER | $41.19 | $35.68 | $76.87 Above median +71% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $37.66 | $24.41 | $62.07 Top 10% +120% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: LANDSCAPE | $21.17 | $13.99 | $35.16 Above median +25% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: SKILLED | $37.66 | $23.97 | $61.63 +118% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LANDSCAPING EQUIPMENT (INCLUDES HYDRO SEEDER OR MULCHER, SOD ROLLER, FARM TRACTOR WITH ATTACHMENT SPECIFICLLY SEEDING, SODDING, OR PLANT, AND TWO-FRAM | $24.00 | $16.96 | $40.96 | $0.00 | $0.00 | $0.00 | $0.00 |
| LATHER | $32.00 | $24.95 | $56.95 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| METERS/164 FEET OF BOOM AND OVER; PILE DRIVING WHEN THREE DRUMS IN USE; TRUCK OR CRAWLER CRANE WITH 150 FEET OF BOOM UP TO AND NOT INCLUDING 200 FEET | $50.64 | $26.90 | $77.54 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| MILLWRIGHT | $37.15 | $19.90 | $57.05 +71% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| OFF-ROAD TRUCK | $27.72 | $19.55 | $47.27 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER | $34.23 | $25.28 | $59.51 Top 10% +103% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAVEMENT MARKING OR MARKING REMOVAL EQUIPMENT (; SELF-PROPELLED TRUCK OR TRAILER MOUNTED UNITS.) | $12.00 | $0.00 | $12.00 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| PILEDRIVER | $26.54 | $17.03 | $43.57 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER/STEAMFITTER | $43.54 | $20.89 | $64.43 +61% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPELAYER | $35.98 | $23.42 | $59.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| PLASTERER | $33.22 | $18.33 | $51.55 Above median +57% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $43.54 | $20.89 | $64.43 Above median +61% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 1: HELICOPTER PILOT; TOWER CRANE 250 FEET AND OVER; TRUCK CRAWLER CRANE WITH 200 FEET OF BOOM AND OVER, INC | $45.24 | $22.85 | $68.09 +80% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 3: ALL-TERRAIN VEHICLE CRANES; CONCRETE PUMP 32-49 METERS/102-164 FEET; DERRICK; SELF-ERECTING TOWER CRANE | $49.05 | $26.90 | $75.95 Top 10% +101% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 4: CRAWLER BACKHOE INCLUDING ATTACHMENTS; FIREPERSON, CHIEF BOILER LICENSE; HOIST ENGINEER; LOCOMOTIVE; OVE | $43.15 | $22.85 | $66.00 +75% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 6: CONCRETE BATCH PLANT; FIREPERSON, FIRST CLASS BOILER LICENSE; FRONT END, SKID STEER UP TO 1 C YD; GUNITE | $26.05 | $13.60 | $39.65 +5% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 8: ELEVATOR OPERATOR; GREASER; MECHANICAL SPACE HEATER | $19.46 | $8.34 | $27.80 -26% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 2: GRADER OR MOTOR PATROL; TUGBOAT 100 H.P. AND OVER WHEN LICENSE REQUIRED | $30.00 | $13.60 | $43.60 +15% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 3: ASPHALT BITUMINOUS STABILIZER PLANT; CABLEWAY; DERRICK; DREDGE OR ENGINEERS, DREDGE AND ENGINEER; LOC | $31.48 | $19.70 | $51.18 Above median +35% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 4: AIR TRACK ROCK DRILL; AUTOMATIC ROAD MACHINE; BACKFILLER OPERATOR; BITUMINOUS ROLLERS, RUBBER TIRED O | $29.58 | $13.60 | $43.18 +14% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 5: BITUMINOUS ROLLER; CONCRETE SAW; FORM TRENCH DIGGER; HYDRAULIC LOG SPLITTER; LOADER; POST HOLE DRIVIN | $27.57 | $13.60 | $41.17 +9% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 6: CAT, CHALLENGER, OR SIMILAR TYPE OF TRACTORS, WHEN PULLING DISK OR ROLLER; DREDGE DECK HAND; GRAVEL S | $24.83 | $13.60 | $38.43 Above median +2% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PUMP/PUMPCRETE OR COMPLACO TYPE; FIREPERSON, TEMPORARY HEAT SECOND CLASS BOILER LICENSE; OILER; PICK UP SWEEPER; PUMP AND/OR CONVEYOR | $43.55 | $26.90 | $70.45 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $37.29 | $21.88 | $59.17 Above median +58% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER | $40.25 | $31.11 | $71.36 Above median +137% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SIGN ERECTOR | $37.19 | $19.88 | $57.07 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $43.53 | $26.67 | $70.20 +75% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SURVEY FIELD TECHNICIAN | $20.00 | $13.96 | $33.96 | $0.00 | $0.00 | $0.00 | $0.00 |
| TERRAZZO WORKER | $41.96 | $22.50 | $64.46 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE FINISHER | $24.55 | $8.56 | $33.11 +11% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE SETTER | $37.11 | $30.59 | $67.70 Top 10% +128% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 1: MECHANIC; TRACTOR TRAILER DRIVER; TRUCK DRIVER | $33.00 | $5.43 | $38.43 +31% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 2: FOUR OR MORE AXLE UNIT, STRAIGHT BODY TRUCK | $38.00 | $6.91 | $44.91 +53% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 3: BITUMINOUS DISTRIBUTOR DRIVER; BITUMINOUS DISTRIBUTOR; THREE AXLE UNITS | $32.79 | $24.70 | $57.49 Top 10% +96% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 4: BITUMINOUS DISTRIBUTOR SPRAY OPERATOR; DUMP PERSON; GREASER; PILOT CAR DRIVER; RUBBER-TIRED, SELF-PROPELLED PACKER UNDER 8 TONS | $21.41 | $13.60 | $35.01 +19% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| UNDERGROUND AND OPEN DITCH LABORER | $36.00 | $24.26 | $60.26 | $0.00 | $0.00 | $0.00 | $0.00 |
| WIRING SYSTEM TECHNICIAN | $47.73 | $22.24 | $69.97 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| WIRING SYSTEMS INSTALLER | $33.44 | $17.82 | $51.26 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Crow Wing, MN — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Crow Wing
Compliance Notes
- This wage determination applies to federal contracts for building construction in Crow Wing, Minnesota.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.