Building Construction — Chippewa, Minnesota

WD MN20260038-15569-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ARTICULATED HAULER in Chippewa, Minnesota (construction type: building) is $24.00/hr base + $6.00/hr fringe = $30.00/hr total package (WD MN20260038-15569-bld, Rev. 1).

Scroll down for all 53 trade classifications covered by this determination.

WD Number: MN20260038-15569-bld
Revision: 1
Construction Type: building
State: Minnesota (MN)
County: Chippewa
Effective: May 17, 2026
Trades covered: 53
Official source: SAM.gov reference MN20260038View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ARTICULATED HAULER $24.00 $6.00 $30.00 Bottom 10% $0.00 $0.00 $0.00 $0.00
ASBESTOS ABATEMENT WORKER $41.23 $25.99 $67.22 Top 10% $0.00 $0.00 $0.00 $0.00
BOILERMAKER $48.35 $31.93 $80.28 Above median +63% vs market $0.00 $0.00 $0.00 $0.00
BOOM TRUCK $19.00 $0.00 $19.00 Bottom 10% $0.00 $0.00 $0.00 $0.00
BRICKLAYER $41.73 $29.01 $70.74 Above median +65% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $33.14 $27.60 $60.74 Above median +95% vs market $0.00 $0.00 $0.00 $0.00
CARPET LAYER $30.65 $20.03 $50.68 Above median +28% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON $50.06 $25.45 $75.51 Top 10% +147% vs market $0.00 $0.00 $0.00 $0.00
DRUMS); MECHANIC; POWER PLANT; PUMP OPERATOR AND/OR CONVEYOR; SELF-ERECTING TOWER CRANE UNDER 100 FEET MEASURED FROM BOOM FOOT PIN; STRADDLE CARRIER $44.54 $26.40 $70.94 $0.00 $0.00 $0.00 $0.00
DRYWALL TAPER $35.31 $24.43 $59.74 Above median +99% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $46.00 $30.00 $76.00 Above median +94% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR CONSTRUCTORS $62.52 $45.36 $107.88 Top 10% +91% vs market $0.00 $0.00 $0.00 $0.00
FLAG PERSON $12.50 $2.95 $15.45 $0.00 $0.00 $0.00 $0.00
GLAZIER $48.98 $26.75 $75.73 Above median +135% vs market $0.00 $0.00 $0.00 $0.00
HEATING AND FROST INSULATORS $26.00 $0.65 $26.65 $0.00 $0.00 $0.00 $0.00
IRONWORKER $44.85 $35.72 $80.57 Above median +80% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $36.06 $24.39 $60.45 Top 10% +114% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $25.75 $18.70 $44.45 Above median +57% vs market $0.00 $0.00 $0.00 $0.00
LABORER: SKILLED $36.06 $24.39 $60.45 +114% vs market $0.00 $0.00 $0.00 $0.00
LANDSCAPING EQUIPMENT (INCLUDES HYDRO SEEDER OR MULCHER, SOD ROLLER, FARM TRACTOR WITH ATTACHMENT SPECIFICALLY SEEDING, SODDING, OR PLANT, AND TWO-FRA $25.75 $18.70 $44.45 $0.00 $0.00 $0.00 $0.00
LATHER $34.19 $25.40 $59.59 Above median $0.00 $0.00 $0.00 $0.00
METERS/164 FEET OF BOOM AND OVER; PILE DRIVING WHEN THREE DRUMS IN USE; TRUCK OR CRAWLER CRANE WITH 150 FEET OF BOOM UP TO AND NOT INCLUDING 200 FEET $48.53 $26.88 $75.41 $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $41.66 $35.40 $77.06 Above median +131% vs market $0.00 $0.00 $0.00 $0.00
PAINTER $31.63 $25.28 $56.91 Above median +94% vs market $0.00 $0.00 $0.00 $0.00
PILEDRIVER $39.96 $21.08 $61.04 $0.00 $0.00 $0.00 $0.00
PIPEFITTER/STEAMFITTER $48.24 $34.70 $82.94 Above median +107% vs market $0.00 $0.00 $0.00 $0.00
PIPELAYER $40.14 $24.24 $64.38 Above median $0.00 $0.00 $0.00 $0.00
PLASTERER $34.40 $14.62 $49.02 +49% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $54.79 $30.58 $85.37 Above median +113% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 1: HELICOPTER PILOT; TOWER CRANE 250 FEET AND OVER; TRUCK CRAWLER CRANE WITH 200 FEET OF BOOM AND OVER, INC $43.35 $22.85 $66.20 +75% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 3: ALL-TERRAIN VEHICLE CRANES; CONCRETE PUMP 32-49 METERS/102-164 FEET; DERRICK; SELF-ERECTING TOWER CRANE $47.02 $26.88 $73.90 +96% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 4: CRAWLER BACKHOE INCLUDING ATTACHMENTS; FIREPERSON, CHIEF BOILER LICENSE; HOIST ENGINEER; LOCOMOTIVE; OVE $41.38 $22.85 $64.23 +70% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 6: CONCRETE BATCH PLANT; FIREPERSON, FIRST CLASS BOILER LICENSE; FRONT END, SKID STEER UP TO 1 C YD; GUNITE $38.55 $22.85 $61.40 +63% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 2: GRADER OR MOTOR PATROL; TUGBOAT 100 H.P. AND OVER WHEN LICENSE REQUIRED $31.00 $8.00 $39.00 +3% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 3: ASPHALT BITUMINOUS STABILIZER PLANT; CABLEWAY; DERRICK; DREDGE OR ENGINEERS, DREDGE AND ENGINEER; LOC $38.00 $8.75 $46.75 +24% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 4: AIR TRACK ROCK DRILL; AUTOMATIC ROAD MACHINE; BACKFILLER OPERATOR; BITUMINOUS ROLLERS, RUBBER TIRED O $30.75 $8.75 $39.50 +5% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 5: BITUMINOUS ROLLER; CONCRETE SAW; FORM TRENCH DIGGER; HYDRAULIC LOG SPLITTER; LOADER; POST HOLE DRIVIN $31.50 $0.00 $31.50 -17% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 6: CAT, CHALLENGER, OR SIMILAR TYPE OF TRACTORS, WHEN PULLING DISK OR ROLLER; DREDGE DECK HAND; GRAVEL S $34.00 $8.50 $42.50 Above median +12% vs market $0.00 $0.00 $0.00 $0.00
PUMP/PUMPCRETE OR COMPLACO TYPE; FIREPERSON, TEMPORARY HEAT SECOND CLASS BOILER LICENSE; OILER; PICK UP SWEEPER; PUMP AND/OR CONVEYOR $41.73 $26.88 $68.61 $0.00 $0.00 $0.00 $0.00
ROOFER $39.01 $21.93 $60.94 Above median +63% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $40.23 $30.02 $70.25 Above median +134% vs market $0.00 $0.00 $0.00 $0.00
SIGN ERECTOR $32.17 $17.65 $49.82 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $43.53 $26.67 $70.20 +75% vs market $0.00 $0.00 $0.00 $0.00
SURVEY FIELD TECHNICIAN $23.00 $8.00 $31.00 $0.00 $0.00 $0.00 $0.00
TERRAZZO WORKER $38.91 $19.40 $58.31 $0.00 $0.00 $0.00 $0.00
TILE FINISHER $14.00 $1.50 $15.50 -48% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 1: MECHANIC; TRACTOR TRAILER DRIVER; TRUCK DRIVER $33.00 $8.75 $41.75 +42% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 2: FOUR OR MORE AXLE UNIT, STRAIGHT BODY TRUCK $33.00 $8.75 $41.75 +42% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 3: BITUMINOUS DISTRIBUTOR DRIVER; BITUMINOUS DISTRIBUTOR; THREE AXLE UNITS $33.00 $8.75 $41.75 +42% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 4: BITUMINOUS DISTRIBUTOR SPRAY OPERATOR; DUMP PERSON; GREASER; PILOT CAR DRIVER; RUBBER-TIRED, SELF-PROPELLED PACKER UNDER 8 TONS $20.00 $1.50 $21.50 Bottom 10% -27% vs market $0.00 $0.00 $0.00 $0.00
UNDERGROUND AND OPEN DITCH LABORER $38.14 $24.24 $62.38 $0.00 $0.00 $0.00 $0.00
WIRING SYSTEM TECHNICIAN $47.73 $22.24 $69.97 Top 10% $0.00 $0.00 $0.00 $0.00
WIRING SYSTEMS INSTALLER $33.44 $17.82 $51.26 Top 10% $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Chippewa, MN — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Chippewa

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MN20260038-15569-bld →