Building Construction — Ingham, Michigan

WD MI20260084-15494-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CH in Ingham, Michigan (construction type: building) is $47.28/hr base + $25.25/hr fringe = $72.53/hr total package (WD MI20260084-15494-bld, Rev. 1).

Scroll down for all 40 trade classifications covered by this determination.

WD Number: MI20260084-15494-bld
Revision: 1
Construction Type: building
State: Michigan (MI)
County: Ingham
Effective: May 17, 2026
Trades covered: 40
Official source: SAM.gov reference MI20260084View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CH $47.28 $25.25 $72.53 $0.00 $0.00 $0.00 $0.00
ASBESTOS WORKER/HEAT & FROST INSULATOR $40.00 $23.65 $63.65 Above median +190% vs market $0.00 $0.00 $0.00 $0.00
BOILERMAKER $43.50 $36.74 $80.24 Above median +151% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER: BRICKLAYER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE $36.10 $26.22 $62.32 +106% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER: TERRAZZO AND TILE FINISHER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WOR $32.20 $20.74 $52.94 +75% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER: TERRAZZO AND TILE SETTER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKI $32.20 $23.46 $55.66 +84% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $36.21 $21.06 $57.27 +94% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER, INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION $36.21 $21.06 $57.27 +94% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $24.64 $12.88 $37.52 Above median +32% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ALARM INSTALLATION & LOW VOLTAGE WIRING $38.79 $19.87 $58.66 +68% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ALARM INSTALLATION & LOW VOLTAGE WIRING $30.00 $10.90 $40.90 +17% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: EXCLUDES ALARM INSTALLATION & LOW VOLTAGE WIRING $36.90 $25.19 $62.09 +78% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: EXCLUDES ALARM INSTALLATION AND LOW VOLTAGE WIRING $56.05 $30.52 $86.57 +148% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, ORNAMENTAL $18.48 $7.93 $26.41 -14% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: REINFORCING $36.55 $33.37 $69.92 Above median +128% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL $36.55 $35.60 $72.15 Above median +135% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE; PIPELAYER; SANDBLASTER $32.53 $13.45 $45.98 +96% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE & IRRIGATION $8.00 $0.00 $8.00 Bottom 10% -66% vs market $0.00 $0.00 $0.00 $0.00
METAL BUILDING ERECTOR $16.92 $6.32 $23.24 Top 10% $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $42.92 $39.13 $82.05 Above median +105% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $21.34 $7.57 $28.91 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BULLDOZER $20.63 $8.21 $28.84 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: GRADER/BLADE $22.00 $6.29 $28.29 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE O $43.93 $25.25 $69.18 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 3 CONCRETE PUMP; CRANE; HIGHLIFT; HOIST; LOADER; ROLLER; SCRAPER; STIFF LEG DERRICK; TRENCHER FOOTNOTES: CRANE OPERAT $41.28 $25.25 $66.53 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.5 $39.57 $25.25 $64.82 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 5 BOOM TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE $39.57 $25.25 $64.82 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 6 FORK TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE $33.71 $25.25 $58.96 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 7 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE $31.23 $25.25 $56.48 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: TRACTOR $19.10 $8.48 $27.58 Top 10% $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER, SPRAY AND PAPERHANGING $28.75 $18.68 $47.43 +100% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: DRYWALL FINISHING/TAPING $28.32 $16.88 $45.20 +90% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER, INCLUDES HVAC PIPE AND UNIT INSTALLATION FOOTNOTE: PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY AND LABOR DAY, IF THE EMPLOYEE WORKS THE $46.29 $25.43 $71.72 +94% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION FOOTNOTE: PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY AND LABOR DAY, IF THE EMPLOYEE WORKS THE WOR $46.29 $25.43 $71.72 +94% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 1 $42.74 $21.53 $64.27 Top 10% +114% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $33.18 $17.22 $50.40 Above median +86% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $41.34 $27.39 $68.73 +86% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $16.00 $7.26 $23.26 Above median -12% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: LOWBOY TRUCK $14.50 $0.44 $14.94 -44% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: TRACTOR HAUL TRUCK $13.57 $1.18 $14.75 Above median -44% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Ingham, MI — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Ingham

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MI20260084-15494-bld →