The Davis-Bacon prevailing wage for CARPENTER, INCLUDES FORM WORK in Clinton, Michigan (construction type: heavy) is $36.21/hr base + $21.06/hr fringe = $57.27/hr total package (WD MI20260055-15470-hvy, Rev. 1).

Scroll down for all 27 trade classifications covered by this determination.

WD Number: MI20260055-15470-hvy
Revision: 1
Construction Type: heavy
State: Michigan (MI)
County: Clinton
Effective: May 17, 2026
Trades covered: 27
Official source: SAM.gov reference MI20260055View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
CARPENTER, INCLUDES FORM WORK $36.21 $21.06 $57.27 Top 10% +94% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $24.64 $12.88 $37.52 Above median +32% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $45.00 $31.37 $76.37 Above median +119% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: REINFORCING $36.55 $33.37 $69.92 Above median +128% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL $36.55 $35.93 $72.48 Above median +136% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( COMMON OR GENERAL) $23.39 $13.15 $36.54 Above median +56% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( GRADE CHECKER) $23.70 $13.15 $36.85 Top 10% +57% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( MASON TENDER-CEMENT/CONCRETE) $23.53 $13.15 $36.68 Top 10% +57% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( PIPELAYER) $23.84 $13.15 $36.99 +58% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - CEMENT/CONCRETE; PIPELAYER $32.53 $13.45 $45.98 Above median +96% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $12.25 $0.00 $12.25 -48% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. FOOTNOTES $48.98 $25.25 $74.23 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE $45.68 $25.25 $70.93 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 BACKHOE/EXCAVATOR; BORING MACHINE; BULLDOZER; CRANE; GRADER/BLADE; LOADER; ROLLE $44.00 $25.25 $69.25 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK FOOTNOTES: CRANE OPERATOR WITH MAI $41.32 $25.25 $66.57 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 5 BOOM TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.5 $41.32 $25.25 $66.57 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6 FORK TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.5 $35.46 $25.25 $60.71 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER AND SPRAY $21.89 $11.85 $33.74 Top 10% +42% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER/PIPEFITTER $42.29 $23.94 $66.23 +79% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, GRADER/ BLADE, LOADER, ROLLER, SCRAPE $45.98 $25.25 $71.23 Top 10% +137% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 2 TRENCHER $41.25 $25.25 $66.50 Top 10% +121% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 3 BOOM TRUCK $40.52 $25.25 $65.77 Top 10% +119% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER $39.95 $25.25 $65.20 Top 10% +117% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $18.00 $6.43 $24.43 Above median -8% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY $33.55 $0.75 $34.30 Top 10% +29% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: OFF THE ROAD TRUCK $20.82 $3.69 $24.51 Above median -8% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: TRACTOR HAUL TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY $33.30 $0.75 $34.05 +28% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Clinton, MI — Heavy construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Clinton

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MI20260055-15470-hvy →