WD MI20260054-15491-hvy · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for 1 RATE in Cass, Michigan (construction type: heavy) is $41.32/hr base + $25.25/hr fringe = $66.57/hr total package (WD MI20260054-15491-hvy, Rev. 1).

Scroll down for all 28 trade classifications covered by this determination.

WD Number: MI20260054-15491-hvy
Revision: 1
Construction Type: heavy
State: Michigan (MI)
County: Cass
Effective: May 17, 2026
Trades covered: 28
Official source: SAM.gov reference MI20260054View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
1 RATE $41.32 $25.25 $66.57 $0.00 $0.00 $0.00 $0.00
CARPENTER, INCLUDES FORM WORK $28.29 $21.42 $49.71 Top 10% +68% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $24.63 $12.88 $37.51 Above median +32% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $46.00 $29.23 $75.23 Above median +115% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL AND REINFORCING $31.75 $22.84 $54.59 Above median +78% vs market $0.00 $0.00 $0.00 $0.00
LABORER $27.21 $13.45 $40.66 Above median +74% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( COMMON OR GENERAL) $22.42 $12.95 $35.37 Above median +51% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( GRADE CHECKER) $22.73 $12.95 $35.68 Above median +52% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( MASON TENDER-CEMENT/CONCRETE) $22.55 $12.95 $35.50 Above median +52% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( PIPELAYER) $22.85 $12.95 $35.80 +53% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $12.25 $0.00 $12.25 -48% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. PAID HOLIDA $48.98 $25.25 $74.23 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE $45.68 $25.25 $70.93 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 BACKHOE/EXCAVATOR; BORING MACHINE; BULLDOZER; CRANE; GRADER/BLADE; LOADER; ROLLE $44.00 $25.25 $69.25 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK PAID HOLIDAYS: NEW YEAR'S DAY, MEM $41.32 $25.25 $66.57 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6 FORK TRUCK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF ULY, LABOR DAY $35.46 $25.25 $60.71 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 7 OILER PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF ULY, LABOR DAY, THA $32.98 $25.25 $58.23 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH & ROLLER $21.75 $11.94 $33.69 +42% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: SPRAY $22.75 $11.94 $34.69 +46% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $33.60 $19.36 $52.96 Above median +43% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, GRADER/ BLADE, LOADER, ROLLER, SCRAPE $45.98 $25.25 $71.23 Top 10% +137% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 2 TRENCHER $41.25 $25.25 $66.50 Top 10% +121% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 3 BOOM TRUCK $40.52 $25.25 $65.77 Top 10% +119% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER $39.95 $25.25 $65.20 Top 10% +117% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $18.00 $6.43 $24.43 Above median -8% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY $33.55 $0.75 $34.30 Top 10% +29% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: OFF THE ROAD TRUCK $20.82 $3.69 $24.51 Above median -8% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: TRACTOR HAUL TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY $33.30 $0.75 $34.05 +28% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Cass, MI — Heavy construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.