Building Construction — Bay, Michigan

WD MI20260077-15469-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CH in Bay, Michigan (construction type: building) is $47.28/hr base + $25.25/hr fringe = $72.53/hr total package (WD MI20260077-15469-bld, Rev. 1).

Scroll down for all 36 trade classifications covered by this determination.

WD Number: MI20260077-15469-bld
Revision: 1
Construction Type: building
State: Michigan (MI)
County: Bay
Effective: May 17, 2026
Trades covered: 36
Official source: SAM.gov reference MI20260077View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CH $47.28 $25.25 $72.53 $0.00 $0.00 $0.00 $0.00
ASBESTOS WORKER/HEAT & FROST INSULATOR $40.00 $23.65 $63.65 Above median +190% vs market $0.00 $0.00 $0.00 $0.00
BOILERMAKER $43.50 $36.74 $80.24 Above median +151% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER IS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY $35.83 $22.18 $58.01 +92% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER, INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION $35.86 $23.69 $59.55 +102% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $25.47 $12.38 $37.85 Above median +33% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $40.00 $26.52 $66.52 Above median +90% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $17.47 $3.10 $20.57 -41% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, ORNAMENTAL $18.48 $7.93 $26.41 -14% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: REINFORCING $36.55 $33.37 $69.92 Above median +128% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL $36.55 $35.93 $72.48 Above median +136% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - BRICK/CEMENT/CONCRETE; PIPELAYER $27.68 $13.45 $41.13 +76% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE AND IRRIGATION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDST $29.93 $9.10 $39.03 +67% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE AND IRRIGATION: GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TEN $27.71 $9.10 $36.81 +57% vs market $0.00 $0.00 $0.00 $0.00
LABORER: SANDBLASTER $28.21 $13.45 $41.66 Top 10% +78% vs market $0.00 $0.00 $0.00 $0.00
LATHER $24.29 $13.66 $37.95 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $18.57 $6.40 $24.97 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $15.93 $8.10 $24.03 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE O $43.93 $25.25 $69.18 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 3 BULLDOZER; CONCRETE PUMP; CRANE; GRADER/BLADE; HIGHLIFT; HOIST; ROLLER; SCRAPER; STIFF LEG DERRICK; TRENCHER FOOTNO $42.25 $25.25 $67.50 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.5 $39.57 $25.25 $64.82 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 5 BOOM TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE $39.57 $25.25 $64.82 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 6 FORK TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE $33.37 $25.25 $58.62 Bottom 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 7 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE $31.23 $25.25 $56.48 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: TRACTOR $19.10 $8.48 $27.58 Top 10% $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER AND SPRAY $29.23 $19.11 $48.34 Top 10% +104% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: DRYWALL FINISHING/TAPING $30.22 $22.22 $52.44 Above median +121% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER, INCLUDES HVAC PIPE AND UNIT INSTALLATION $46.00 $22.99 $68.99 Above median +86% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION $46.00 $22.99 $68.99 Above median +86% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $30.38 $19.87 $50.25 Above median +86% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $26.83 $23.78 $50.61 +71% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $41.34 $27.39 $68.73 +86% vs market $0.00 $0.00 $0.00 $0.00
TILE FINISHER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER IS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLI $26.24 $21.13 $47.37 +84% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER IS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDA $31.43 $21.13 $52.56 +105% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK $12.00 $0.00 $12.00 -55% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: TRACTOR HAUL TRUCK $13.57 $1.18 $14.75 Above median -44% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Bay, MI — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.