Building Construction — Nantucket, Massachusetts

WD MA20260001-15433-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for BOILERMAKER in Nantucket, Massachusetts (construction type: building) is $50.62/hr base + $28.82/hr fringe = $79.44/hr total package (WD MA20260001-15433-bld, Rev. 1).

Scroll down for all 100 trade classifications covered by this determination.

WD Number: MA20260001-15433-bld
Revision: 1
Construction Type: building
State: Massachusetts (MA)
County: Nantucket
Effective: May 17, 2026
Trades covered: 100
Official source: SAM.gov reference MA20260001View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BOILERMAKER $50.62 $28.82 $79.44 Above median $0.00 $0.00 $0.00 $0.00
BRICKLAYER (BOSTON CHAPTER MIDDLESEX; NORFOLK; AND SUFFOLK) $64.50 $37.54 $102.04 Top 10% +125% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER (LOWELL CHAPTER MIDDLESEX; AND NORFOLK) $60.26 $33.71 $93.97 Bottom 10% +107% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER AND PLASTERER (LOWELL CHAPTER MIDDLESEX) $60.26 $33.71 $93.97 +107% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER AND PLASTERER (WALTHAM CHAPTER MIDDLESEX) $64.50 $37.54 $102.04 +125% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER, CEMENT MASON AND PLASTERER (LYNN CHAPTER ESSEX; AND MIDDLESEX) $64.50 $37.54 $102.04 +125% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER, CEMENT MASON AND PLASTERER (NEW BEDFORD BARNSTABLE; BRISTOL; DUKES; AND NANTUCKET COUNTIES) $64.50 $37.54 $102.04 +125% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER, CEMENT MASON AND PLASTERER (NEWTON CHAPTER MIDDLESEX AND NORFOLK) $64.50 $37.54 $102.04 +125% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER, CEMENT MASON AND PLASTERER (QUINCY CHAPTER NORFOLK COUNTY) $64.50 $37.54 $102.04 +125% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER, CEMENT MASON, PLASTERER (FOXBORO CHAPTER BRISTOL AND NORFOLK COUNTIES) $60.26 $33.71 $93.97 +107% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $46.43 $28.35 $74.78 Top 10% +119% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER (BARNSTABLE; BRISTOL; AND NORFOLK COUNTIES) $39.28 $27.90 $67.18 +96% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER (BRISTOL; ESSEX; MIDDLESEX; AND NORFOLK) $50.10 $31.45 $81.55 +139% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER (MIDDLESEX; NORFOLK; AND SUFFOLK) $61.19 $31.55 $92.74 +171% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER (NORFOLK COUNTY) $50.10 $31.45 $81.55 +139% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $49.19 $40.86 $90.05 Top 10% +193% vs market $0.00 $0.00 $0.00 $0.00
DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 Y $41.14 $37.35 $78.49 Top 10% $0.00 $0.00 $0.00 $0.00
DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 Y $41.02 $37.35 $78.37 Bottom 10% $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (BARNSTABLE; BRISTOL; DUKES; NANTUCKET AND NORFOLK) $50.02 $31.05 $81.07 +105% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (BRISTOL) $56.11 $24.74 $80.85 Top 10% +105% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (ESSEX) $66.17 $37.08 $103.25 Top 10% +162% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (ESSEX; MIDDLESEX) $66.17 $37.08 $103.25 Top 10% +162% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (ESSEX; MIDDLESEX; NORFOLK (BELLINGHAM, BRAINTREE, BROOKLINE, CANTON, COHASSET, DEDHAM, DOVER, FOXBORO, FRANKLOIN, MEDFIELD, MEDWAY, MILLI $66.17 $37.08 $103.25 Top 10% +162% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (MIDDLESEX) $48.16 $36.20 $84.36 Top 10% +114% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTE FOR ELEVATOR MECHANICS: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BAS $74.17 $38.44 $112.61 Top 10% +74% vs market $0.00 $0.00 $0.00 $0.00
FLOOR LAYER: CARPET $49.18 $31.75 $80.93 Top 10% +162% vs market $0.00 $0.00 $0.00 $0.00
FLOOR LAYER: CARPET (MIDDLESEX; NORFOLK; AND SUFFOLK) $57.49 $31.75 $89.24 +189% vs market $0.00 $0.00 $0.00 $0.00
GLAZIER $46.26 $36.00 $82.26 Above median +68% vs market $0.00 $0.00 $0.00 $0.00
GLAZIER FOOTNOTE: A. PAID HOLIDAY: LABOR DAY $43.13 $21.00 $64.13 +31% vs market $0.00 $0.00 $0.00 $0.00
HAZARDOUS MATERIAL HANDLER: INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS $55.45 $36.63 $92.08 Top 10% $0.00 $0.00 $0.00 $0.00
INSULATOR/ASBESTOS WORKER ZONE A- BARNSTABLE COUNTY BRISTOL COUNTY, MIDDLESEX COUNTY, AND NORFOLK COUNTY $55.45 $36.63 $92.08 +235% vs market $0.00 $0.00 $0.00 $0.00
INSULATOR/ASBESTOS WORKER ZONE B- BARNSTABLE COUNTY, BRISTOL COUNTY,AND NORFOLK COUNTY $55.45 $36.63 $92.08 +235% vs market $0.00 $0.00 $0.00 $0.00
INSULATOR/ASBESTOS WORKER: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHES TO ALL TYPES OF MECHANICA $55.45 $36.63 $92.08 +235% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER (BARNSTABLE; BRISTOL; DUKES; NANTUCKET; NORFOLK) $43.03 $33.53 $76.56 +37% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER (MIDDLESEX; NORFOLK) $57.57 $37.67 $95.24 Top 10% +70% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS $53.46 $37.67 $91.13 Top 10% +63% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS $57.87 $37.67 $95.54 Top 10% +70% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 1- LABORERS; CARPENTER TENDERS (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESSEX; NANTUCKET; MIDDLESEX; NORFOLK) $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 1- LABORERS; CARPENTER TENDERS (SUFFOLK COUNTY; MIDDLESEX COUNTY; NORFOLK COUNTY) $46.10 $29.70 $75.80 +152% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 2 - JACKHAMMER OPERATOR; PAVEMENT BREAKER; ASPHALT RAKER CARBIDE CORE DRILLING MACHINE; CHAIN SAW OPERATOR; PIPELAYER; BARCO TYPE JUMP $46.10 $29.70 $75.80 +152% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 2- JACKHAMMER OPERATOR; PAVEMENT BREAKER; ASPHALT RAKER CARBIDE CORE DRILLING MACHINE; CHAIN SAW OPERATOR; PIPELAYER; BARCO TYPE JUMPI $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 3- AIR TRACK, BLOCK PAVER; HAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESS $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 3- AIR TRACK, BLOCK PAVER; RAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (SUFFOLK COUNTY; MIDDLESEX COUNTY; NORFOLK C $46.10 $29.70 $75.80 +152% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 4- BLASTER; POWDERMAN (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESSEX; NANTUCKET; MIDDLESEX; NORFOLK) $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 4- BLASTER; POWDERMAN (SUFFOLK COUNTY; MIDDLESEX COUNTY; NORFOLK COUNTY) $46.10 $29.70 $75.80 Bottom 10% +152% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 5- PRE-CAST FLOOR AND ROOF PLANK ERECTOR (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESSEX; NANTUCKET; MIDDLESEX; NORFOLK) $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 5- PRE-CAST FLOOR AND ROOF PLANK ERECTOR (SUFFOLK COUNTY; MIDDLESEX COUNTY; NORFOLK COUNTY) $46.10 $29.70 $75.80 +152% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 6- ASBESTOS REMOVAL LABORERS/HAZ-MAT LABORERS (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESSEX; NANTUCKET; MIDDLESEX; NORFOLK) $46.10 $29.70 $75.80 +152% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 6- ASBESTOS REMOVAL LABORERS/HAZ-MAT LABORERS (SUFFOLK COUNTY; MIDDLESEX COUNTY; NORFOLK COUNTY) $46.10 $29.70 $75.80 +152% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 7 - FLAGGERS (SUFFOLK COUNTY; MIDDLESEX COUNTY; NORFOLK COUNTY) $27.01 $29.70 $56.71 +89% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, HEAVY CONSTRUCTION: GROUP 1 LABORERS; CARPENTER TENDERS; CEMENT FINISHER TENDERS, PLASTERER TENDERS $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, HEAVY CONSTRUCTION: GROUP 2 ASPHALT RAKER; FENCE AND GUARD RAIL ERECTOR; LASER BEAM OPERATOR; MASON TENDER; PIPELAYER; PNEUMATIC DRILL OPER $39.20 $29.70 $68.90 +130% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, HEAVY CONSTRUCTION: GROUP 3 AIR TRACK OPERATOR; BLOCK PAVER; RAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF POWERED DRILLS $39.70 $29.70 $69.40 +131% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, HEAVY CONSTRUCTION: GROUP 4 BLASTER; POWDERMAN $39.95 $29.70 $69.65 +132% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, HEAVY CONSTRUCTION: GROUP 5 FLAGGER $39.70 $29.70 $69.40 +131% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, HEAVY CONSTRUCTION: GROUP 6 ASBESTOS ABATEMENT; TOXIC AND HAZARDOUS WASTE LABORERS $40.95 $29.70 $70.65 +135% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, WRECKING: GROUP 5 YARDMAN, BURNERS, SAWYERS...$ 45.35 29.70 LABORERS:, WRECKING: GROUP 4 YARDMAN...$ 42.25 29.70 LABORERS:, WRECKING: GROUP $47.00 $29.70 $76.70 +155% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, WRECKING: GROUP 6 ASBESTOS, LEAD PAINT, TOXIC AND HAZARDOUS WASTE $46.25 $29.70 $75.95 Top 10% +153% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: EQUIPMENT OPERATOR A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY AND $49.65 $26.72 $76.37 Top 10% +49% vs market $0.00 $0.00 $0.00 $0.00
LISTED HOLIDAYS $58.41 $30.19 $88.60 Top 10% $0.00 $0.00 $0.00 $0.00
LISTED HOLIDAYS $32.13 $12.70 $44.83 Bottom 10% $0.00 $0.00 $0.00 $0.00
MARBLE & TILE FINISHER $49.32 $35.26 $84.58 Top 10% $0.00 $0.00 $0.00 $0.00
MARBLE, TILE & TERRAZZO WORKERS $64.52 $37.51 $102.03 Top 10% $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $50.47 $33.50 $83.97 Above median +167% vs market $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $45.03 $33.25 $78.28 Above median +149% vs market $0.00 $0.00 $0.00 $0.00
NANTUCKET; PLYMOUTH) $53.25 $29.75 $83.00 Top 10% $0.00 $0.00 $0.00 $0.00
OVER 295 FT. +11.86 OVER 350 FT. +13.82 $30.85 $33.70 $64.55 Bottom 10% $0.00 $0.00 $0.00 $0.00
OVER 295 FT. +11.86 OVER 350 FT. +13.82 $46.52 $33.70 $80.22 Above median $0.00 $0.00 $0.00 $0.00
OVER 295 FT. +11.86 OVER 350 FT. +13.82 $37.02 $33.70 $70.72 $0.00 $0.00 $0.00 $0.00
OVER 295 FT. +11.86 OVER 350 FT. +13.82 $57.83 $33.70 $91.53 Top 10% $0.00 $0.00 $0.00 $0.00
PAINTER BRUSH, TAPER $44.32 $36.00 $80.32 Bottom 10% +199% vs market $0.00 $0.00 $0.00 $0.00
PAINTER BRUSH, TAPER $46.26 $36.00 $82.26 Top 10% +206% vs market $0.00 $0.00 $0.00 $0.00
PAINTER SPRAY, SANDBLAST $45.72 $36.00 $81.72 Bottom 10% +204% vs market $0.00 $0.00 $0.00 $0.00
PAINTER SPRAY, SANDBLAST $47.66 $36.00 $83.66 Top 10% +211% vs market $0.00 $0.00 $0.00 $0.00
PILEDRIVERMAN (SUFFOLK; AND THOSE AREAS OF BARNSTABLE, BRISTOL, ESSEX, MIDDLESEX & NORFOLK COUNTIES SITUATED INSIDE BOSTON BELTWAY AND NORTH OF CAPE C $55.79 $35.47 $91.26 $0.00 $0.00 $0.00 $0.00
PILEDRIVERMAN (THE AREAS OF BARNSTABLE, BRISTOL, AND NORFOLK COUNTIES SITUATED OUTSIDE BOSTON BELTWAY AND SOUTH OF CAPE COD CANAL) $55.79 $35.47 $91.26 $0.00 $0.00 $0.00 $0.00
PILEDRIVERMAN (THOSE AREAS OF ESSEX AND MIDDLESEX COUNTIES SITUATED OUTSIDE BOSTON BELTWAY) $49.19 $35.47 $84.66 Top 10% $0.00 $0.00 $0.00 $0.00
PIPEFITTER (ESSEX; MIDDLESEX (ACTON, ARLINGTON, ASHFORD, AYER-EXCEPT WEST OF GREENVILLE BRANCH OF BOSTON & MAINE RAIL ROAD, BEDFORD, BELMONT, BILL $66.58 $39.22 $105.80 +164% vs market $0.00 $0.00 $0.00 $0.00
PLASTERER TENDER $38.95 $29.70 $68.65 Top 10% +66% vs market $0.00 $0.00 $0.00 $0.00
PLASTERER TENDER (BARNSTABLE, BRISTOL, DUKES, ESSEX, NANTUCKET, MIDDLESEX; NORFOLK COUNTIES) $38.95 $29.70 $68.65 +66% vs market $0.00 $0.00 $0.00 $0.00
PLASTERER TENDER (SUFFOLK COUNTY; MIDDLESEX COUNTY; NORFOLK COUNTY) $46.10 $29.70 $75.80 +84% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER (ESSEX) $69.84 $36.43 $106.27 Top 10% +165% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER (ESSEX; MIDDLESEX (ACTON, ARLINGTON, ASHFORD, AYER-EXCEPT WEST OF GREENVILLE BRANCH OF BOSTON & MAINE RAIL ROAD, BEDFORD, BELMONT, BILLERI $69.84 $36.43 $106.27 +165% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS AND PIPEFITTERS (BARNSTABLE; BRISTOL; DUKES; NANTUCKET; AND NORFOLK COUNTIES) $52.49 $33.60 $86.09 +115% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS AND PIPEFITTERS (MIDDLESEX) $55.00 $31.57 $86.57 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 SONIC OR VIBRATORY HAMMER; GRADER; SCRAPER; TANDEM SCRAPER; CONCRETE PUMP; BULLDOZER; TRACTOR; YORK RAKE; MULCHING $57.18 $33.70 $90.88 +160% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 5 OILER FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, LABOR DAY, M $25.02 $33.70 $58.72 +68% vs market $0.00 $0.00 $0.00 $0.00
ROOFERS $53.53 $35.69 $89.22 Top 10% +156% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER (ESSEX; MIDDLESEX; NORFOLK; PLYMOUTH; SUFFOLK) $60.00 $48.78 $108.78 Top 10% +186% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER (BRISTOL (PORTION WITHIN 35 MILE RADIUS FROM BOSTON CITY HALL; MIDDLESEX; NORFOLK; PLYMOUTH; SUFFOLK) A. PAID HOLIDAYS: MEMORIAL DAY $72.05 $40.76 $112.81 +182% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER (BRISTOL) A. PAID HOLIDAYS: MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS BEEN IN $64.85 $40.76 $105.61 +164% vs market $0.00 $0.00 $0.00 $0.00
TELEDATA SYSTEM INSTALLER (BARNSTABLE; BRISTOL; DUKES; NANTUCKET AND NORFOLK) $42.52 $28.47 $70.99 $0.00 $0.00 $0.00 $0.00
TELEDATA SYSTEM INSTALLER (BRISTOL) $42.09 $19.71 $61.80 Top 10% $0.00 $0.00 $0.00 $0.00
TELEDATA SYSTEM INSTALLER (MIDDLESEX) $36.12 $34.51 $70.63 Top 10% $0.00 $0.00 $0.00 $0.00
TERRAZZO FINISHER $63.44 $37.33 $100.77 Top 10% $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 STATION WAGONS; PANEL TRUCKS; AND PICKUP TRUCKS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HA $40.78 $37.35 $78.13 Top 10% +168% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 TWO AXLE EQUIPMENT; & FORKLIFT OPERATOR POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HAZARDOUS $40.95 $37.35 $78.30 Top 10% +169% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 5 SPECIALIZED EARTH MOVING EQUIPMENT UNDER 35 TONS OTHER THAN CONVENTIONAL TYPE TRUCKS; LOW BED; VACHUAL; MECHANICS, PAVING RESTO $41.24 $37.35 $78.59 Top 10% +170% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 6 SPECIALIZED EARTH MOVING EQUIPMENT OVER 35 TONS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HA $41.53 $37.35 $78.88 Top 10% +171% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 7 TRAILERS FOR EARTH MOVING EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATE $41.82 $37.35 $79.17 Top 10% +172% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Nantucket, MA — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Nantucket

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MA20260001-15433-bld →