Building Construction — Tazewell, Illinois
WD IL20260003-16743-bld · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for BASE MACHINE MEN: BASE MACHINE OPERATOR in Tazewell, Illinois (construction type: building) is $34.16/hr base + $24.46/hr fringe = $58.62/hr total package (WD IL20260003-16743-bld, Rev. 1).
Scroll down for all 33 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| BASE MACHINE MEN: BASE MACHINE OPERATOR | $34.16 | $24.46 | $58.62 | $0.00 | $0.00 | $0.00 | $0.00 |
| BOILERMAKER | $45.23 | $32.76 | $77.99 +70% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $36.83 | $24.47 | $61.30 Above median +48% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER, BUILDING: JOURNEYMAN | $33.58 | $29.10 | $62.68 +71% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER, BUILDING: PILEDRIVERMAN | $34.58 | $29.10 | $63.68 +73% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER: RESIDENTIAL | $30.22 | $29.10 | $59.32 +62% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $31.48 | $30.33 | $61.81 Above median +66% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $39.50 | $24.24 | $63.74 Above median +38% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $26.58 | $18.50 | $45.08 -3% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| GLAZIER | $39.74 | $27.78 | $67.52 Above median +134% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER | $39.24 | $33.88 | $73.12 Above median +51% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER GROUP 1 GENERAL LABORER - AIR TAMPER; BRICKLAYER TENDER; HAZARDOUS WASTE WORKER; CARPENTER TENDER; CEMENT MASON AND SACK SHAKERS; CEMENT MASON | $34.00 | $33.28 | $67.28 +116% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER GROUP 2 SKILLED LABORER - CONCRETE SPECIALIST; CUTTING AND ACETYLENE TORCH; GUNNITE NOZZLEMEN; GUNNITE PUMP MEN AND POTS; KETTLEMEN AND CARRIE | $34.40 | $33.28 | $67.68 +117% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER GROUP 3ASBESTOS ABATEMENT WORKER; LEAD BASE PAINT ABATEMENT WORKER; HAZARDOUS WASTE WORKER (PEORIA AND TAZEWELL COUNTIES) | $36.00 | $33.28 | $69.28 +122% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: BUILDING (TAZEWELL COUNTY) | $34.00 | $30.04 | $64.04 +105% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| MARBLE & TILE SETTER AND TERRAZZO WORKER | $37.60 | $24.48 | $62.08 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| MILLWRIGHT | $33.06 | $29.97 | $63.03 +74% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT: GROUP 1 OVERHEAD CRANES; GRADALL; ALL ROUGH TERRAIN HYDRAULIC CRANES 91,000 LBS GROSS VEHICLE WEIGHT AND OVER REQUIRE AN OI | $47.79 | $43.42 | $91.21 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT: GROUP 2 DINKEYS; POWER LAUNCHES; PH ONE-PASS SOIL-CEMENT MACHINE; PUGMILL WITH PUMP; BACKFILLERS; EUCLID LOADER; FORKLIFTS | $44.09 | $43.42 | $87.51 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT: GROUP 3 AIR COMPRESSOR; HERMAN NELSON HEATER, DRAVO, WARNER, SILENT GLO, AND SIMILAR TYPES; WATER PUMP; LIGHT PLANTS; GENER | $38.03 | $43.42 | $81.45 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH, SPRAY, PRESSURE ROLLER, SANDBLASTING, BRIDGES, & NEW STRUCTURAL STEEL WORK | $40.00 | $26.90 | $66.90 Top 10% +123% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER | $41.10 | $27.59 | $68.69 Above median +49% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLASTERER | $31.00 | $30.07 | $61.07 Above median +53% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $42.70 | $30.98 | $73.68 Above median +59% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $38.05 | $24.60 | $62.65 Above median +95% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER | $28.18 | $33.06 | $61.24 Above median +36% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER | $39.50 | $33.06 | $72.56 Above median +61% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 1: DRIVERS ON 2 AXLES HAULING LESS THAN 9 TONS; AIR COMPRESSOR & WELDING MACHINES AND BROOMS, INCLUDING THOSE PULLED BY SEPARATE U | $43.24 | $24.27 | $67.51 +135% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 3- 2, 3 OR 4 AXLES HAULING 16 TONS OR MORE; 5-AXLES OR MORE COMBINATION UNITS; DRIVERS ON WATER PULLS; ARTICULATED DUMP TRUCKS; ME | $44.10 | $24.27 | $68.37 +138% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 4: LOW BOY AND OIL DISTRIBUTORS | $44.49 | $24.27 | $68.76 +139% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 5: DRIVERS WHO REQUIRE SPECIAL PROTECTIVE CLOTHING WHILE EMPLOYED ON HAZARDOUS WASTE WORK | $45.59 | $24.27 | $69.86 +143% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| VACATION PAY CREDIT FORE EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE; AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE B) PAID HOLIDAYS: NEW YEAR'S DAY; MEMO | $57.99 | $38.44 | $96.43 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| WINCH TRUCKS; HYDROLIFT TRUCKS; VACTOR TRUCKS OR SIMILAR EQUIPMENT WHEN USED FOR TRANSPORTATION PURPOSES; FORKLIFT OVER 6,000 LB.CAPACITY; WINCH TRUCK | $43.83 | $24.27 | $68.10 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Tazewell, IL — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Tazewell
Compliance Notes
- This wage determination applies to federal contracts for building construction in Tazewell, Illinois.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.