Building Construction — Sangamon, Illinois

WD IL20260004-16769-bld · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS WORKER/HEAT & FROST INSULATOR in Sangamon, Illinois (construction type: building) is $43.48/hr base + $27.24/hr fringe = $70.72/hr total package (WD IL20260004-16769-bld, Rev. 2).

Scroll down for all 31 trade classifications covered by this determination.

WD Number: IL20260004-16769-bld
Revision: 2
Construction Type: building
State: Illinois (IL)
County: Sangamon
Effective: May 17, 2026
Trades covered: 31
Official source: SAM.gov reference IL20260004View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKER/HEAT & FROST INSULATOR $43.48 $27.24 $70.72 Above median +195% vs market $0.00 $0.00 $0.00 $0.00
BOILERMAKER $45.50 $35.30 $80.80 Above median +76% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $28.48 $25.74 $54.22 +48% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER - PILEDRIVER $32.64 $25.74 $58.38 +59% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER AND LATHER $31.64 $25.74 $57.38 +56% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $28.51 $21.93 $50.44 Above median +35% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN Residential Construction $24.83 $17.12 $41.95 -9% vs market $0.00 $0.00 $0.00 $0.00
GLAZIER $39.77 $22.73 $62.50 Above median +117% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER $36.20 $31.35 $67.55 Above median +39% vs market $0.00 $0.00 $0.00 $0.00
LABORER $32.90 $29.26 $62.16 Above median +99% vs market $0.00 $0.00 $0.00 $0.00
LABORER $35.90 $29.26 $65.16 Top 10% +109% vs market $0.00 $0.00 $0.00 $0.00
MARBLE, TILE & TERRAZZO WORKERS $32.20 $18.51 $50.71 $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $33.06 $29.36 $62.42 +72% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: BUILDING EPOXY OR TOXIC-LEAD-BASED PAINT WORK-$1.00 PREMIMUM ALL WORK OVER 40 FT. ABOVE FLOOR OR GROUND LEVEL - $1.00 PREMIUM $32.23 $20.58 $52.81 +76% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: RESIDENTIAL EPOXY OR TOXIC-LEAD-BASED PAINT WORK-$1.00 PREMIMUM ALL WORK OVER 40 FT. ABOVE FLOOR OR GROUND LEVEL - $1.00 PREMIUM $29.73 $20.58 $50.31 +68% vs market $0.00 $0.00 $0.00 $0.00
PLASTERER $28.50 $19.12 $47.62 +19% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, PIPEFITTER, STEAMFITTER $37.88 $25.71 $63.59 Bottom 10% +37% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, PIPEFITTER, STEAMFITTER $43.89 $25.71 $69.60 +50% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 1 ASPHALT PLANT ENGINEER; ASPHALT SCREED MAN; APSCO CONCRETE SPREADER; ASPHALT PAVER; ASPHALT ROLLER ON BITUMINOUS CONT $40.71 $28.75 $69.46 Above median +49% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 2 ASPHALT BOOSTER & HEATER; ASPHALT DISTRIBUTOR; ASPHALT PLANT FIREMAN;BUILDING ELEVATOR; BULL FLOAT OR FLEXPLANE; CONC $38.18 $28.75 $66.93 Bottom 10% +44% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 3 AIR COMPRESSOR, TRACK OR SELF-PROPELLED; BULK CEMENT BATCHING- PLANTS; CONVEYORS; CONCRETE MIERS FIREMENT, GENERATORS $34.30 $28.75 $63.05 Top 10% +35% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 4 LATTICE BOOM CRAWLER CRANE, LATTICE BOOM TRUCK CRANE, TELESCOPIC TRUCK MOUNTED CRANE, TOWER CRANE PREMIUM PAY- CRANES $42.32 $28.75 $71.07 Top 10% +52% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $36.00 $26.36 $62.36 Above median +94% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $26.73 $26.48 $53.21 +18% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $38.54 $30.37 $68.91 Above median +53% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 1: DRIVERS ON 2 AXLES HAULING LESS THAN 9 TONS; AIR COMPRESSOR & WELDING MACHINES AND BROOMS, INCLUDING THOSE PULLED BY SEPARATE U $45.35 $25.72 $71.07 +147% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 3- 2, 3 OR 4 AXLES HAULING 16 TONS OR MORE; 5-AXLES OR MORE COMBINATION UNITS; DRIVERS ON WATER PULLS; ARTICULATED DUMP TRUCKS; ME $46.25 $25.72 $71.97 +150% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 4: LOW BOY AND OIL DISTRIBUTORS $46.60 $25.72 $72.32 +152% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 5: DRIVERS WHO REQUIRE SPECIAL PROTECTIVE CLOTHING WHILE EMPLOYED ON HAZARDOUS WASTE WORK $47.71 $25.72 $73.43 +155% vs market $0.00 $0.00 $0.00 $0.00
VACATION PAY CREDIT FORE EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE; AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE B) PAID HOLIDAYS: NEW YEAR'S DAY; MEMO $57.99 $38.44 $96.43 Above median $0.00 $0.00 $0.00 $0.00
WINCH TRUCKS; HYDROLIFT TRUCKS; VACTOR TRUCKS OR SIMILAR EQUIPMENT WHEN USED FOR TRANSPORTATION PURPOSES; FORKLIFT OVER 6,000 LB.CAPACITY; WINCH TRUCK $45.93 $25.72 $71.65 Top 10% $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Sangamon, IL — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.