Building Construction — Kane, Illinois

WD IL20260008-16713-bld · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS WORKER/INSULATOR in Kane, Illinois (construction type: building) is $55.02/hr base + $35.75/hr fringe = $90.77/hr total package (WD IL20260008-16713-bld, Rev. 2).

Scroll down for all 112 trade classifications covered by this determination.

WD Number: IL20260008-16713-bld
Revision: 2
Construction Type: building
State: Illinois (IL)
County: Kane
Effective: May 17, 2026
Trades covered: 112
Official source: SAM.gov reference IL20260008View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKER/INSULATOR $55.02 $35.75 $90.77 Top 10% +279% vs market $0.00 $0.00 $0.00 $0.00
BOILERMAKER $53.10 $38.54 $91.64 Top 10% +100% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER $48.56 $34.05 $82.61 Top 10% +99% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER $44.88 $26.62 $71.50 Above median +72% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $45.61 $35.31 $80.92 Top 10% +120% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER, CARPENTER, MILLWRIGHT, PILEDRIVER, AND SOFT FLOOR LAYER $45.61 $35.31 $80.92 Top 10% +120% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER: BUILDING $52.01 $38.85 $90.86 Top 10% +147% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER: CARPENTER, FLOOR LAYER, LATHER, MILLWRIGHT, AND PILEDRIVER $52.01 $38.86 $90.87 Top 10% +147% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER: HEAVY & HIGHWAY $52.01 $38.85 $90.86 Above median +147% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER; MILLWRIGHT; PILEDRIVERMEN $52.01 $41.41 $93.42 Top 10% +154% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $50.70 $40.60 $91.30 Top 10% +145% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $46.25 $45.10 $91.35 Top 10% +145% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $48.50 $42.82 $91.32 Top 10% +145% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $38.00 $24.03 $62.03 Above median +67% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: BUILDING $51.87 $51.77 $103.64 Top 10% +124% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: BUILDING $52.00 $45.01 $97.01 Bottom 10% +109% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: BUILDING (KANE AND KENDALL COUNTIES) $60.17 $43.50 $103.67 Top 10% +124% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: BUILDING (KANE AND MCHENRY COUNTIES) $59.11 $42.23 $101.34 Top 10% +119% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ELECTRICAL TECHNICIAN: WORK INCLUDES THE INSTALLATION, MAINTENANCE AND REMOVAL OF TELECOMMUNICATION FACILITIES, TELEPHONE, SECURITY, FIRE $48.71 $35.87 $84.58 +83% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ELECTRICAL TECHNICIAN: WORK INCLUDES THE INSTALLATION, MAINTENANCE AND REMOVAL OF TELECOMMUNICATION FACILITIES, TELEPHONE, SECURITY, FIRE $48.00 $39.85 $87.85 Above median +90% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ELECTRICAL TECHNICIAN: WORK INCLUDES THE INSTALLATION, MAINTENANCE AND REMOVAL OF TELECOMMUNICATION FACILITIES, TELEPHONE, SECURITY, FIRE $44.00 $37.91 $81.91 Bottom 10% +77% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ELECTRICAL TECHNICIAN: WORK INCLUDES THE INSTALLATION, MAINTENANCE AND REMOVAL OF TELECOMMUNICATION FACILITIES, TELEPHONE, SECURITY, FIRE $49.70 $38.45 $88.15 Top 10% +90% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ELECTRICAL TECHNICIAN: WORK INCLUDES THE INSTALLATION, MAINTENANCE AND REMOVAL OF TELECOMMUNICATION FACILITIES, TELEPHONE, SECURITY, FIRE $40.90 $44.32 $85.22 Above median +84% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: RESIDENTIAL $39.60 $32.25 $71.85 Top 10% +55% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: RESIDENTIAL (KANE AND MCHENRY COUNTIES) $44.40 $34.59 $78.99 Top 10% +70% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTES: A) PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; DAY AFTER THANKSGIVING DAY $70.68 $38.44 $109.12 Top 10% +75% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTES: A. EMPLOYER CONTRIBUTES 8% OF REGULAR BASIC HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SE $57.99 $38.44 $96.43 Top 10% +54% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC MCHENRY COUNTY) FOOTNOTES: A. EMPLOYER CONTRIBUTES 8% OF REGULAR BASIC HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE TH $61.96 $38.44 $100.40 Top 10% +61% vs market $0.00 $0.00 $0.00 $0.00
FIRE STOP TECHNICIAN $44.02 $32.76 $76.78 Top 10% $0.00 $0.00 $0.00 $0.00
GLAZIER $51.55 $44.09 $95.64 Top 10% +232% vs market $0.00 $0.00 $0.00 $0.00
HAZARDOUS MATERIAL HANDLER $41.27 $32.76 $74.03 Above median $0.00 $0.00 $0.00 $0.00
INSIDE A SPHERE OR ANY TYPE OR MAKE OF TANK; WORKING INSIDE A SPHERE OR ANY TYPE OR MAKE OF TANK FROM BOTTOM TO A HEIGHT OF 48 FEET; FORM STRIPPERS; M $47.40 $33.16 $80.56 Bottom 10% $0.00 $0.00 $0.00 $0.00
IRONWORKER (DUPAGE, GRUNDY, KENDALL, AND WILL COUNTIES) $47.80 $42.50 $90.30 Top 10% +86% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER (DUPAGE, KANE, KENDALL, AND MCHENRY COUNTIES) $48.83 $39.84 $88.67 Top 10% +83% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER (MCHENRY COUNTY) $41.37 $44.41 $85.78 Top 10% +77% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, ORNAMENTAL (LAKE, DUPAGE AND MCHENRY COUNTIES) $59.26 $44.81 $104.07 Top 10% +114% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: FENCE ERECTOR (LAKE, DUPAGE, AND MCHENRY COUNTIES) $52.25 $34.31 $86.56 Top 10% +78% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: MACHINERY MOVERS; RIGGERS; MACHINERY ERECTORS (LAKE, DUPAGE AND MCHENRY COUNTIES) $54.25 $47.38 $101.63 Top 10% +109% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: MASTER RIGGERS (LAKE, DUPAGE AND MCHENRY COUNTIES) $56.75 $47.38 $104.13 Top 10% +114% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: SHEETER (DU PAGE, LAKE, AND MCHENRY COUNTIES) $62.71 $46.58 $109.29 Top 10% +125% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL AND REINFORCING (DU PAGE, LAKE, AND MCHENRY COUNTIES) $62.46 $46.58 $109.04 Top 10% +125% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 1 BUILDING LABORERS, PLASTERER TENDERS, PUMPS FOR DEWATERING & OTHER UNCLASSIFIED LABORERS $51.40 $36.94 $88.34 Top 10% +183% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 1 BUILDING LABORERS; PLASTERER TENDERS, GENERAL LABORERS; FIREPROOFING AND FIRE SHOP LABORERS $51.40 $36.94 $88.34 Top 10% +183% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 10 BOILER SETTER PLASTIC LABORERS $51.85 $36.94 $88.79 Bottom 10% +185% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 10 BOILER SETTER PLASTIC LABORERS $51.95 $36.94 $88.89 Top 10% +185% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 11 DOSIMETER MONITORING NUCLEAR EXPOSURE; ASBESTOS ABATEMENT LABORERS; TOXIC AND HAZARDOUS WASTE REMOVAL LABORERS $51.60 $36.94 $88.54 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 11 JACKHAMMERMEN ON FIRE BRICK WORK ONLY $51.68 $36.94 $88.62 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 12 DOSIMETER MONITORING NUCLEAR EXPOSURE); ASBESTOS ABATEMENT LABORERS; TOXIC AND HAZARDOUS WASTE REMOVAL LABORERS $52.40 $36.94 $89.34 Top 10% +186% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 2 CEMENT GUN LABORERS AND HOSE $51.48 $36.94 $88.42 Top 10% +183% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 2 FIREPROOFING AND FIRE SHOP LABORERS $51.40 $36.94 $88.34 Top 10% +183% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 2 SEWER AND DRAIN PIPE LAYERS AND MULTIPLE CONCRETE DUCT OR ANY OTHER TYPE OF PIPE USED, ON PUBLIC UTILITY WORK; PUMPCRETE PIPE HANDLERS $47.40 $33.16 $80.56 Bottom 10% +158% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 3 ASPHALT RAKERS; HOD CARRIERS; PLASTERER LABORERS; GUNNITE LABORERS, SLAB FOR SETTERS ON ROADS, HIGHWAYS, STREETS, AIRPORT RUNAWAYS, AN $47.48 $33.16 $80.64 Bottom 10% +158% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 3 CEMENT GUN LABORERS AND HOSE $51.48 $36.94 $88.42 Top 10% +183% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 3 CHIMNEY OVER 40 FEET; SCAFFOLD LABORERS; WALL MEN OR WRECKERS $51.50 $36.94 $88.44 Top 10% +183% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 4 CEMENT GUN NOZZLE LABORERS $51.60 $36.94 $88.54 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 4 CHIMNEY OVER 40 FEET; SCAFFOLD LABORERS; WELDMAN-WRECKERS BURNERS $51.50 $36.94 $88.44 Top 10% +183% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 5 CEMENT GUN NOZZLE LABORERS; WINDLASS AND CAPSTAN PERSON $51.55 $36.94 $88.49 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 5 GUNNITE NOZZLE MEN; CAISSON LABORERS AND ALL TAMPING HAMMERS FROM 150 LBS AND OVER; FROM 15 FEET BELOW GROUND LEVEL DOWN TO 50 FEET; A $47.60 $33.16 $80.76 Top 10% +159% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 5 JACKHAMMER & AIRSPADE; CHAINSAW, SWINGING STAGE AND BOATSWAIN CHAIR; CEMENT GUN NOZZLEMAN; HOD CARRIER; PLASTERER TENDER, AND TUNNEL M $51.65 $36.94 $88.59 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 5 STONE DERRICKMEN AND HANDLERS $51.60 $36.94 $88.54 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 6 ALL UNDERGROUND CAVERN LABORERS; CAISSON LABORERS 50 FEET OR MORE BELOW GROUND LEVEL; LABORERS WORKING UNDER RADIO ACTIVE CONDITIONS $47.75 $33.16 $80.91 Bottom 10% +159% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 6 JACKHAMMERMEN; POWER DRIVEN CONCRETE SAWS $51.63 $36.94 $88.57 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 6 STONE DERRICKMEN AND HANDLERS $51.60 $36.94 $88.54 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 6 TILE LAYERS; BOTTOM MEN KANE, KENDALL, AND MCHENRY COUNTIES $52.10 $36.94 $89.04 Top 10% +185% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 7 CAISSON LABORERS; DYNAMITERS KANE, KENDALL, AND MCHENRY COUNTIES $52.10 $36.94 $89.04 Top 10% +185% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 7 DOSIMETER USED FOR MONITORING NUCLEAR EXPOSURE; ASBESTOS ABATEMENT WORKER; TOXIC AND HAZARDOUS WASTE REMOVAL LABORER; AND CHIMNEY AND $47.60 $33.16 $80.76 Bottom 10% +159% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 7 FIREBRICK & BOILER LABORER SETTERS $51.73 $36.94 $88.67 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 7 JACKHAMMERMEN, POWER DRIVEN CONCRETE SAWS AND OTHER POWER EQUIPMENT $51.63 $36.94 $88.57 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 8 ASBESTOS ABATEMENT LABORERS, TOXIC AND HAZARDOUS WASTE REMOVAL LABORERS, DOSIMETER MONITORING NUCLEAR EXPOSUREANE KENDALL, AND MCHENRY $51.80 $36.94 $88.74 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 8 CHIMNEY LABORERS; CAISSON DIGGERS; WELL POINT SYSTEM MEN $51.75 $36.94 $88.69 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 8 FIREBRICK & BOILER LABORERS $51.73 $36.94 $88.67 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 9 CHIMNEY ON FIRE BRICK; CAISSON DIGGERS; WELL POINT SYSTEM MEN $51.75 $36.94 $88.69 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER GROUP 9 WINDLASS AND CAPSTAN PERSONS $51.60 $36.94 $88.54 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 1 COMMON LABORER KANE, KENDALL, AND MCHENRY COUNTIES $51.40 $36.94 $88.34 Top 10% +183% vs market $0.00 $0.00 $0.00 $0.00
LABORER: GROUP 2 POWER VIBRATOR KANE, KENDALL, AND MCHENRY COUNTIES $51.65 $36.94 $88.59 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN $48.44 $29.09 $77.53 Top 10% +52% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: LINEMAN AND EQUIPMENT OPERATOR $62.10 $37.29 $99.39 Top 10% +95% vs market $0.00 $0.00 $0.00 $0.00
MARBLE FINISHER $33.95 $26.03 $59.98 $0.00 $0.00 $0.00 $0.00
MARBLE SETTER $47.71 $33.20 $80.91 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, GROUP 1 MECHANIC; ASPHALT PLANT*; ASPHALT SPREADER; AUTOGRADE*; BACKHOES WITH CAISSON ATTACHMENT*:BATCH PLANT*; BENOTO; BOI $64.80 $51.00 $115.80 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, GROUP 2 BOBCAT; BOILERS; BRICK FORKLIFT; BROOM, POWER PROPELLED; BULLDOZERS; CONCRETE MIXER; CONVEYOR, PORTABLE; FORKLIFT T $63.50 $51.00 $114.50 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, GROUP 4 BOBCATS AND/OR OTHER SKID STEER LOADERS; BRICK FORKLIFTS; OILERS $59.20 $51.00 $110.20 Top 10% $0.00 $0.00 $0.00 $0.00
PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION $45.09 $13.40 $58.49 Top 10% $0.00 $0.00 $0.00 $0.00
PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION $44.89 $13.40 $58.29 Above median $0.00 $0.00 $0.00 $0.00
PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION $44.69 $13.40 $58.09 Above median $0.00 $0.00 $0.00 $0.00
PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION $44.54 $13.40 $57.94 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, DECORATOR, AND PAPERHANGER $53.05 $33.91 $86.96 Top 10% +190% vs market $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, DRYWALL TAPER/FINISHER, SANDBLASTER, AND SPRAY $53.05 $27.63 $80.68 Top 10% +169% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER (DUPAGE, GRUNDY, LAKE, MCHENRY & WILL COUNTIES) $55.00 $38.62 $93.62 Top 10% +102% vs market $0.00 $0.00 $0.00 $0.00
PLASTERER $42.25 $26.65 $68.90 Above median +73% vs market $0.00 $0.00 $0.00 $0.00
PLASTERER $49.65 $42.17 $91.82 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $45.76 $26.92 $72.68 Above median +57% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER/PIPEFITTER (DUPAGE, KANE, AND KENDALL COUNTIES) $41.20 $29.15 $70.35 Top 10% +52% vs market $0.00 $0.00 $0.00 $0.00
PUMPS, WELL POINTS; WELDING MACHINES; WINCHES, 4 SMALL ELECTRIC DRILL WINCHES; BOBCAT $60.95 $51.00 $111.95 Top 10% $0.00 $0.00 $0.00 $0.00
ROOFER $50.25 $30.43 $80.68 Top 10% +151% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $38.50 $27.23 $65.73 Above median +104% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $49.10 $42.91 $92.01 Top 10% +105% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $56.35 $38.65 $95.00 Top 10% +111% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER: ALUMINUM GUTTER WORK $31.32 $37.02 $68.34 Top 10% +52% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $63.25 $36.50 $99.75 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
TERRAZZO WORKER/SETTER $48.38 $30.79 $79.17 Above median +58% vs market $0.00 $0.00 $0.00 $0.00
TILE FINISHER $42.80 $26.97 $69.77 Top 10% +172% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $49.75 $30.79 $80.54 Top 10% +214% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: 2 OR 3 AXLE TRUCKS FOOTNOTES: A. $448.80 HEALTH & WELFARE PER WEEK, $562.80 PENSION PER WEEK. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR $46.12 $0.30 $46.42 Top 10% +61% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: 2-3 AXLES FOOTNOTE: A. AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX AXLES. LOW-BOY IS AN ADDITIONAL $1 $45.31 $0.30 $45.61 Top 10% +59% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: 4 AXLE TRUCKS FOOTNOTES: A. $448.80 HEALTH & WELFARE PER WEEK, $562.80 PENSION PER WEEK. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN AD $46.27 $0.30 $46.57 Top 10% +62% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: 4 AXLES FOOTNOTE: A. AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX AXLES. LOW-BOY IS AN ADDITIONAL $1.50 $45.46 $0.30 $45.76 Top 10% +59% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: 5 AXLE TRUCKS FOOTNOTES: A. $448.80 HEALTH & WELFARE PER WEEK, $562.80 PENSION PER WEEK. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN AD $46.47 $0.30 $46.77 Top 10% +63% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: 5 AXLES FOOTNOTE: A. AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX AXLES. LOW-BOY IS AN ADDITIONAL $1.50 $45.66 $0.30 $45.96 Top 10% +60% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: 6 AXLE TRUCKS FOOTNOTES: A. $448.80 HEALTH & WELFARE PER WEEK, $562.80 PENSION PER WEEK. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN AD $46.67 $0.30 $46.97 Top 10% +63% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: 6 AXLES FOOTNOTE: A. AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX AXLES. LOW-BOY IS AN ADDITIONAL $1.50 $45.86 $0.30 $46.16 Top 10% +61% vs market $0.00 $0.00 $0.00 $0.00
VIBRATORS-ANY TYPE-8 FEET OR MORE BELOW GROUND LEVEL $47.60 $33.16 $80.76 Bottom 10% $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Kane, IL — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Kane

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for IL20260008-16713-bld →