Highway Construction — Jefferson, Arkansas
WD AR20260166-16252-hwy · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for CARPENTER, INCLUDES FORM WORK in Jefferson, Arkansas (construction type: highway) is $17.00/hr base + $0.00/hr fringe = $17.00/hr total package (WD AR20260166-16252-hwy, Rev. 1).
Scroll down for all 37 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| CARPENTER, INCLUDES FORM WORK | $17.00 | $0.00 | $17.00 -24% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $16.39 | $0.00 | $16.39 -26% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| HIGHWAY/PARKING LOT STRIPING: OPERATOR | $13.25 | $0.00 | $13.25 | $0.00 | $0.00 | $0.00 | $0.00 |
| HIGHWAY/PARKING LOT STRIPING: PAINTER | $21.75 | $0.00 | $21.75 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, REINFORCING | $14.22 | $0.00 | $14.22 -40% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, STRUCTURAL | $17.46 | $0.00 | $17.46 -26% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $14.68 | $0.00 | $14.68 -18% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $12.23 | $0.00 | $12.23 -31% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $11.15 | $0.00 | $11.15 -37% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $14.33 | $0.00 | $14.33 -19% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: ASPHALT SPREADER | $15.39 | $0.00 | $15.39 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $14.55 | $0.00 | $14.55 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $16.06 | $0.00 | $16.06 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BROOM/SWEEPER | $12.00 | $0.00 | $12.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BULLDOZER | $15.54 | $0.00 | $15.54 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CRANE | $22.84 | $0.00 | $22.84 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: DRILL | $14.85 | $0.00 | $14.85 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: GRADE CHECKER | $14.68 | $0.00 | $14.68 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: GRADER/BLADE | $17.66 | $0.00 | $17.66 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: HYDROSEEDER | $10.79 | $0.00 | $10.79 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: LOADER | $16.74 | $0.00 | $16.74 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: MECHANIC | $23.68 | $0.00 | $23.68 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: MILLING MACHINE | $17.28 | $0.00 | $17.28 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: OILER | $19.29 | $0.00 | $19.29 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: PAVER | $17.17 | $0.00 | $17.17 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POST DRIVER | $16.96 | $0.00 | $16.96 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: ROLLER | $12.83 | $0.00 | $12.83 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: SCRAPER | $19.31 | $0.00 | $19.31 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: SCREED | $15.01 | $0.00 | $15.01 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: TRACTOR | $10.00 | $0.00 | $10.00 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| TRAFFIC CONTROL: FLAGGER | $10.00 | $0.00 | $10.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | $10.50 | $0.00 | $10.50 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $13.80 | $0.00 | $13.80 -42% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: FLATBED TRUCK | $21.03 | $0.00 | $21.03 Above median -12% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: LOWBOY TRUCK | $16.63 | $0.00 | $16.63 -30% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: SEMI/TRAILER TRUCK | $12.50 | $0.00 | $12.50 -48% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: WATER TRUCK | $13.17 | $0.00 | $13.17 -45% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Jefferson, AR — Highway construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Jefferson
Compliance Notes
- This wage determination applies to federal contracts for highway construction in Jefferson, Arkansas.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.